CS Professional · Strategic Management and Corporate Finance · Project Evaluation
A project's base-case NPV is Rs 6,00,000. The firm finds that NPV falls to zero if sales volume falls 20% from the base estimate, but NPV falls to zero only if the cost of capital rises 60%. What does this indicate about the project's risk?
The project is more sensitive to sales volume, because only a 20% fall in sales brings NPV to zero, whereas the cost of capital must rise 60%. In sensitivity analysis, the variable with the smaller break-even change is the more critical one.
- AThe project is more sensitive to sales volume than to cost of capital, so sales volume is the more critical variableCorrect
- BThe project is more sensitive to cost of capital than to sales volume
- CThe project has no risk because NPV is positive
- DBoth variables are equally critical
Explanation
A smaller percentage change in sales (20%) wipes out the NPV than for the cost of capital (60%), so NPV is more sensitive to sales volume. Management should focus on forecasting and controlling sales. Option B reverses this logic.
Did you get it right without looking?
One question tells you little. A timed set on Project Evaluation shows your real accuracy, how long you take and where you lose marks.
More Project Evaluation questions
- Sundaram Foods Ltd is assessing a project costing Rs 1,00,000 giving a single inflow of Rs 1,21,000 at the end of Year 2, with no other cash…
- Two mutually exclusive projects, A and B, are evaluated by Kaveri Engineering Ltd. Project A has IRR 22% and NPV Rs 3,00,000 at the cost of …
- A project has an initial outlay of Rs 8,00,000 and the present value of its future cash inflows at the firm's cost of capital is Rs 9,20,000…
- Which of the following is a standard reason why NPV and IRR may rank mutually exclusive projects differently?
- Which of the following cash flows should be EXCLUDED when computing the incremental cash flows of a new project at Mehta Foods Ltd?
- Which statement about financing costs in estimating project cash flows for NPV analysis is correct?