CS Professional · Strategic Management and Corporate Finance · Project Evaluation
Aarav Textiles is evaluating a machine costing Rs 10,00,000 with cash inflows of Rs 2,00,000 in year 1, Rs 3,00,000 in year 2, Rs 4,00,000 in year 3 and Rs 5,00,000 in year 4. Assuming inflows accrue evenly through each year, the payback period is:
The payback period is 3.2 years. Cumulative inflows reach Rs 9,00,000 after three years, leaving Rs 1,00,000 to be recovered from year four's Rs 5,00,000 inflow, which takes 0.2 of a year.
- A3.0 yearsCorrect
- B3.4 years
- C2.8 years
- D3.25 years
Explanation
Cumulative inflows: year 1 = 2,00,000; year 2 = 5,00,000; year 3 = 9,00,000. Remaining 1,00,000 is recovered in year 4 at 5,00,000 per year, i.e. 0.2 year. Payback = 3.2 years.
Did you get it right without looking?
One question tells you little. A timed set on Project Evaluation shows your real accuracy, how long you take and where you lose marks.
More Project Evaluation questions
- While estimating incremental cash flows for a proposed project, which of the following items should be EXCLUDED from the analysis?
- In capital budgeting, the 'certainty equivalent' approach to adjusting for project risk works by:
- A project's base-case NPV is Rs 6,00,000. The firm finds that NPV falls to zero if sales volume falls 20% from the base estimate, but NPV fa…
- Kaveri Engineering Ltd has a project with a present value of cash inflows of ₹9,00,000 and an initial outlay of ₹7,50,000. Which statement a…
- Under capital rationing with divisible independent projects, which ranking criterion best selects projects to maximise total NPV from a limi…
- A project of Narmada Foods Ltd costs ₹1,00,000 and returns ₹1,21,000 in a single lump sum at the end of Year 2. What is its IRR?