CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Malabar Shipyards Ltd. borrowed ₹1,00,00,000 at 12% p.a. on 1 April 2025 specifically to build an office complex. Construction started on 1 April 2025 and the complex was completed and ready for its intended use on 31 December 2025. The company's year ends on 31 March 2026. What amount of interest on this loan should be charged to the Statement of Profit and Loss for the year?
₹3,00,000 should be charged to profit and loss. Interest for the nine months of construction, ₹9,00,000, is capitalised, but capitalisation ceases once the asset is ready for its intended use on 31 December 2025, so the remaining three months of interest is an expense.
- A₹12,00,000
- B₹9,00,000
- C₹3,00,000Correct
- DNil
Explanation
Annual interest is ₹12,00,000, or ₹1,00,000 per month. Capitalisation stops when the asset is substantially ready for its intended use, so 9 months, ₹9,00,000, is capitalised. Interest for January to March 2026, ₹3,00,000, is expensed. Charging nothing wrongly capitalises the whole year.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Malabar Constructions Ltd. was building a bridge-linked office complex, a qualifying asset. Active development was suspended for 4 months be…
- Sundaram Textiles Ltd. began constructing a new dyeing unit on 1 April 2025. It borrowed Rs 2,00,00,000 specifically for the project at 9% p…
- Konkan Textiles Ltd. began constructing a new dyeing unit on 1 April 2025. It borrowed Rs 2,00,00,000 specifically for the project at 9% p.a…
- Ganga Power Ltd. is building a power unit, a qualifying asset, from 1 April 2025. A specific loan of Rs 40,00,000 at 11% p.a. was taken on 1…
- Vindhya Engineering Ltd. is building a plant (a qualifying asset) financed from its general borrowings. During the year, the expenditure on …
- Meenakshi Pharma Ltd. took a specific loan of Rs 1,20,00,000 at 10% p.a. on 1 April 2025 to build a plant. Its general borrowings were Rs 80…