CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Meena Textiles Ltd. began constructing a new factory on 1 April 2025 using a specific loan of ₹50,00,000 at 9% p.a. Active development was suspended from 1 August 2025 to 30 November 2025 due to a labour dispute, which is not a normal part of the construction process. Construction resumed on 1 December 2025 and continued to 31 March 2026. Ignoring any investment income, what interest should be capitalised for the year and what should be charged to profit and loss?
₹3,00,000 is capitalised and ₹1,50,000 is charged to profit and loss. AS 16 requires suspension of capitalisation during extended periods when active development is interrupted, so only 8 of the 12 months of interest on ₹4,50,000 qualifies for capitalisation.
- ACapitalised ₹4,50,000; charged ₹0
- BCapitalised ₹3,00,000; charged ₹1,50,000Correct
- CCapitalised ₹3,75,000; charged ₹75,000
- DCapitalised ₹1,50,000; charged ₹3,00,000
Explanation
Total interest = 50,00,000 × 9% = ₹4,50,000. Active development was on for 4 months (April–July) plus 4 months (December–March) = 8 months, so capitalised = 4,50,000 × 8/12 = ₹3,00,000. Suspension of 4 months gives ₹1,50,000 charged to P&L, as capitalisation is suspended during extended periods of suspended active development.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Godavari Power Ltd took a specific loan of ₹5 crore at 9% p.a. on 1 April to build a plant. Active development was interrupted for two month…
- Vindhya Cements Ltd. is building a plant, which is a qualifying asset. Construction started on 1 April 2025. Because of a labour dispute, ac…
- Konark Engineering Ltd took a term loan of Rs 10,00,00,000 at 12% p.a. on 1 April 2025 solely to build a new plant. Physical construction wa…
- Sundaram Textiles Ltd. took a specific term loan of Rs 2,00,00,000 at 10% p.a. on 1 April 2025 to construct a new weaving unit, which is a q…
- Kaveri Infra Ltd. took a specific loan of Rs 50,00,000 at 10% p.a. on 1 April to construct a warehouse (a qualifying asset). Construction st…
- Kaveri Power Ltd took a foreign currency loan of USD 1,00,000 on 1 April 2025 to finance a plant that is a qualifying asset and remained und…