CA Final · Advanced Financial Management
Advanced Capital Budgeting Decisions: formula sheet
Key formulas
- Net Present Value
- NPV = Σ [CFt ÷ (1 + k)^t] − Initial outlay
- k is the cost of capital. Accept if NPV > 0. Rank mutually exclusive projects by higher NPV.
- Internal Rate of Return (interpolation)
- IRR = L + [NPV at L ÷ (NPV at L − NPV at H)] × (H − L)
- L is the lower trial rate (NPV positive), H the higher trial rate (NPV negative). Accept if IRR > cost of capital. The result is an approximation.
- Profitability Index
- PI = PV of cash inflows ÷ PV of cash outflows
- PI > 1 is the same as NPV > 0. Equivalent to 1 + (NPV ÷ outlay) when there is a single initial outlay.
- Modified IRR
- MIRR = (Terminal value of inflows ÷ PV of outflows)^(1 ÷ n) − 1
- Terminal value = Σ CFt × (1 + r)^(n − t), with r the reinvestment rate. Outflows are discounted at the finance rate. n is the project life.
- Payback period
- Payback = Years before full recovery + (Unrecovered outlay ÷ Cash flow of the recovery year)
- Uses cumulative cash flows. Assumes cash flows are spread evenly within the year. For discounted payback, use cumulative present values.
- Accounting-based check: Average rate of return
- ARR = Average annual accounting profit ÷ Average (or initial) investment
- Use the base the question states. Uses profit, not cash, and ignores time value.
- Annual after-tax operating cash flow (CFAT)
- CFAT = (Revenue − Cash costs − Depreciation) × (1 − t) + Depreciation
- Same as (Revenue − Cash costs) × (1 − t) + Depreciation × t. Interest is excluded.
- Depreciation tax shield
- Tax shield = Depreciation × tax rate
- Depreciation itself is non-cash. Only the tax saved is a cash benefit.
- After-tax value of a cash item
- After-tax cash = Pre-tax amount × (1 − t)
- Use for taxable inflows and deductible costs, including opportunity costs such as forgone rent.
- Initial outlay
- Outlay = Asset cost + Installation and other capitalised costs + Initial working capital − After-tax proceeds of any old asset sold
- Sunk costs are never included.
- Terminal cash flow
- Terminal = Salvage value − Tax on gain (or + tax saved on loss) + Working capital released
- Tax on salvage depends on the gain or loss over book value, as the question assumes.
- Fisher relationship
- (1 + Nominal rate) = (1 + Real rate) × (1 + Inflation rate)
- Real rate = (1 + Nominal) ÷ (1 + Inflation) − 1. Do not just subtract inflation unless told to approximate.
- Inflated cash flow
- Nominal CF in year n = Real CF × (1 + inflation)^n
- Apply the specific inflation rate for each item if rates differ for revenue and costs.
- Change in working capital
- Cash flow = −(Working capital needed this year − Working capital at last year-end)
- A rise is an outflow. The balance is released at the end of the project life.
- NPV at risk-adjusted discount rate
- NPV = Σ [CFt ÷ (1 + kr)^t] − Initial outlay, where kr = Rf + risk premium
- Use kr for every year. A riskier project gets a higher kr. Accept if NPV > 0.
- Certainty equivalent coefficient
- α(t) = Certain (CE) cash flow ÷ Risky expected cash flow, with 0 ≤ α ≤ 1
- A lower α means the management is less sure of that year's cash flow.
- NPV by certainty equivalent method
- NPV = Σ [α(t) × CFt ÷ (1 + Rf)^t] − Initial outlay
- Discount at the risk-free rate only. Do not use the RADR here, or you count risk twice.
- Sensitivity (percentage change)
- Sensitivity = % change in NPV ÷ % change in the variable
- The variable with the larger result is the more critical one.
- Break-even change in a variable
- Allowable fall in an inflow-type variable (%) = NPV ÷ PV of that variable × 100
- For the outlay, allowable rise (%) = NPV ÷ Initial outlay × 100. Holds when only that one variable changes and the NPV is positive.
- Expected NPV across scenarios
- Expected NPV = Σ (Probability of scenario × NPV of scenario)
- Probabilities across scenarios must add up to 1.
- Equivalence of RADR and CE
- α(t) = [(1 + Rf) ÷ (1 + kr)]^t, for a constant risk premium
- Shows that RADR implies a CE factor that falls geometrically each year.
- Expected NPV
- E(NPV) = Σ pᵢ × NPVᵢ
- Probabilities across all outcomes must add up to 1.
- Expected cash flow and ENPV
- E(CFₜ) = Σ p × CFₜ; ENPV = Σ E(CFₜ) ÷ (1 + k)ᵗ − Initial outlay
- Use this when probabilities are given on yearly cash flows, not on NPVs.
- Standard deviation
- σ = √[Σ pᵢ × (xᵢ − x̄)²]
- x̄ is the expected value. Weight each squared deviation by its probability.
- Coefficient of variation
- CV = σ ÷ Expected NPV
- Use to compare projects with different ENPVs. Lower CV means lower relative risk. Meaningful only when ENPV is positive.
- σ of NPV, independent yearly cash flows
- σ(NPV) = √[Σ σₜ² ÷ (1 + k)²ᵗ]
- Use only when cash flows of different years are independent.
- σ of NPV, perfectly correlated cash flows
- σ(NPV) = Σ σₜ ÷ (1 + k)ᵗ
- Use when a good year is always followed by a good year.
- Probability of a negative NPV (normal assumption)
- Z = (0 − ENPV) ÷ σ
- Read the area from the normal table. State the normal-distribution assumption.
- Joint (path) probability in a tree
- P(path) = P(first branch) × P(second branch | first branch)
- Multiply along the path. Never add.
- Rolling back
- Chance node value = Σ p × value of branch; Decision node value = highest branch value
- Deduct costs incurred on a branch before comparing.
- Profitability index (PI)
- PI = PV of cash inflows ÷ PV of cash outflows (initial outlay)
- Use present value of future inflows over the outlay. If outflows also occur in later years, use their present value in the denominator.
- NPV and PI link
- NPV = PV of inflows − PV of outflows; PI = 1 + (NPV ÷ Outlay)
- NPV > 0 means PI > 1. Some books define PI as NPV ÷ Outlay; read the question and stay consistent.
- Divisible projects rule
- Rank by PI (highest first); accept in order until budget ends; take a fraction of the last project = Balance funds ÷ Its outlay
- Total NPV = full NPVs of accepted projects + fraction × NPV of the part-accepted project. Valid for a single-period budget.
- Indivisible projects rule
- Select the combination with Σ outlay ≤ budget that gives the highest Σ NPV
- Check feasible combinations. Do not stop at PI ranking. Leftover funds can be assumed to earn only their cost, so they add no NPV unless stated.
- Linear programming form
- Maximise Σ (NPVj × xj) subject to Σ (Cjt × xj) ≤ Bt for each period t; 0 ≤ xj ≤ 1 (divisible) or xj = 0 or 1 (indivisible)
- Cjt is the cash outlay of project j in period t, and Bt is the budget available in period t. Add extra constraints for mutually exclusive or contingent projects.
- Annuity factor
- PVAF(r, n) = [1 − (1 + r)^−n] ÷ r
- Use the table value if the question gives one. Use the same rate throughout.
- Equivalent annual cost (EAC)
- EAC = PV of all costs over the life ÷ PVAF(r, n)
- PV of costs = initial outlay + PV of operating costs + PV of any later repairs − PV of salvage. Choose the lowest EAC.
- Equivalent annual benefit (EAB)
- EAB = NPV ÷ PVAF(r, n)
- Use when the project has inflows. Choose the highest EAB, only among projects with positive NPV.
- Replacement chain NPV (finite)
- Chain NPV = NPV × [1 + (1 + r)^−n + (1 + r)^−2n + ...] up to the common life
- Each repetition's NPV is discounted back by the number of years elapsed before it starts.
- Infinite replacement NPV
- NPV∞ = NPV × (1 + r)^n ÷ [(1 + r)^n − 1]
- Applies when the project is repeated forever with the same cash flows. It ranks projects the same way as EAB.
- Adjusted Present Value
- APV = Base-case NPV + PV of financing side effects
- Base-case NPV uses Ku. Side effects include tax shield, issue costs, subsidy benefit.
- Base-case NPV
- Base-case NPV = Σ [CFt ÷ (1 + Ku)^t] − Initial outlay
- Cash flows are unlevered: no interest deducted, taxed as if no debt.
- Annual interest tax shield
- Tax shield = Interest × Tax rate
- Discount at the cost of debt (Kd) unless the question says otherwise.
- Subsidised loan benefit
- Benefit = Loan amount − PV of repayments at market Kd (after-tax adjusted if asked)
- Use the market rate for discounting the concessional loan's cash flows.
- Ku using asset beta (CAPM)
- Ku = Risk-free rate + Asset beta × Market risk premium
- Use the unlevered or asset beta when given. Follow the method the question specifies.
- Unlevering the beta
- Asset beta = Equity beta × E ÷ (E + D × (1 − t)); with no tax, Asset beta = Equity beta × E ÷ (E + D)
- E and D are market values of equity and debt, t is the tax rate. Unlever the equity beta first, then use the asset beta in CAPM to get Ku.
- Value with real option
- Expanded NPV = Static NPV + Option value
- Option value is a probability-weighted gain, or a binomial or Black-Scholes value.
- Abandonment option payoff
- Value at decision point = Max (PV of continuing, Salvage value)
- Like a put option with salvage value as the exercise price.
- Expansion option payoff
- Value at decision point = Max (0, PV of expansion inflows − Expansion cost)
- Like a call option; exercise only if positive.
Quick revision
- NPV = Σ cash flow ÷ (1 + k)^t minus initial outlay; accept if NPV > 0.
- Use incremental, after-tax cash flows only; ignore sunk costs and include opportunity costs.
- Depreciation is not a cash flow; include only its tax shield = depreciation × tax rate.
- Add back working capital recovery and salvage value (after tax) in the final year.
- Profitability index = PV of inflows ÷ initial outlay; accept if PI > 1.
- For mutually exclusive projects, NPV is the safer guide when it conflicts with IRR.
- Expected NPV = Σ probability × NPV of each outcome.
- Decision trees are solved by rolling back from the last decision to the first.
- Under capital rationing, pick the combination with the highest total NPV within the budget.
- EAC = NPV of costs ÷ annuity factor for the asset's life; choose the lower EAC.
- APV = base-case NPV (all-equity) + PV of financing side effects such as interest tax shield.
- Real options such as expand, abandon or defer add value that plain NPV misses.
Common mistakes
- Choosing the project with the higher IRR when the projects are mutually exclusive and NPV ranks them the other way. Fix: Follow NPV for mutually exclusive projects. State the cause of the conflict (scale or timing) and the crossover rate if given.
- Using the wrong discount rate, such as the IRR or the coupon rate, instead of the cost of capital. Fix: Use the rate the question labels as the cost of capital or required return. Underline it before you start.
- Deducting interest from cash flows and also discounting at the cost of capital Fix: Leave interest out of project cash flows. The cost of capital already compensates for financing.
- Treating depreciation as a cash outflow, or ignoring it altogether Fix: Deduct it only to find tax, then add it back. Its only cash effect is the tax shield, Depreciation × t.
- Discounting CE cash flows at the risk-adjusted rate or the cost of capital. Fix: In the CE method risk is already removed from the cash flow. Discount at the risk-free rate only.
- Applying the CE factor to the discounted cash flow instead of the cash flow. Fix: Multiply the cash flow by α first, then discount. Both orders give the same figure for a single year, but write the formula in the correct order for the marks.
- Taking the expected value of the cash flows and then using it as if it were the NPV, without discounting or deducting the outlay. Fix: Discount each year's expected cash flow, add them, and then deduct the outlay. Alternatively, find each scenario's NPV first and then average.
- Adding probabilities along a path in a tree instead of multiplying. Fix: Multiply along a path to get the joint probability. Add only the probabilities of different paths that end in the same outcome.
- Using PI ranking alone for indivisible projects Fix: For indivisible projects, always compare total NPV across feasible combinations. PI ranking can leave funds idle and miss a better mix.
- Ranking by NPV instead of PI for divisible projects Fix: Under a budget limit you want the most NPV per rupee of outlay. Rank by PI when projects are divisible.
Exam tips
- In written answers, show the table of cash flows and discount factors first. Marks are given for each step even if the final figure is off.
- When the question gives a single IRR trial rate or a table, use only those values. Do not switch to your own calculator figures midway.
- If two mutually exclusive projects are given, calculate NPV and IRR for both and comment on the conflict. The comment on cause and the final NPV-based recommendation usually carry marks.
- For MCQ case scenarios, check the decision rule first. For example, if NPV is positive then PI is above 1 and IRR is above the cost of capital for conventional flows. This can remove options without calculation.
- State assumptions where the question is silent, such as year-end cash flows and the reinvestment rate used for MIRR.
- Draw a year-wise table with rows for outlay, operating CFAT, working capital, salvage and tax, even if the question does not ask. Marks are given for each item.
- Write a one-line note for each exclusion (sunk cost, interest, allocated overhead). Examiners reward stated assumptions.
- If the question gives no tax treatment for salvage, state your assumption clearly before you apply it, and apply it consistently.