CMA Intermediate · Cost Accounting
Standard Costing and Variance Analysis: formula sheet
Key formulas
- Standard cost per unit
- Standard material + Standard labour + Standard overhead (variable and fixed)
- Each element is built as standard quantity (or time) × standard price (or rate).
- Standard material cost
- Standard quantity per unit × Standard price per unit of material
- Standard quantity includes normal loss or wastage allowed.
- Standard labour cost
- Standard hours per unit × Standard wage rate per hour
- Standard hours include allowance for normal idle time and fatigue where applicable.
- Standard overhead rate
- Budgeted overheads ÷ Budgeted base (units or hours)
- Calculate separately for variable and fixed overheads.
- Standard overhead cost per unit
- Standard overhead rate × Standard hours (or units) per unit
- Base must be the same one used to compute the rate.
- Standard input for given output
- Standard input = Standard output ÷ (1 − normal loss %)
- Use when the question gives output required and a normal loss percentage on input.
- Material cost variance (MCV)
- MCV = (SQ × SP) − (AQ × AP)
- SQ is the standard quantity for actual output. A positive result is favourable.
- Material price variance (MPV)
- MPV = AQ × (SP − AP)
- Use AQ purchased if the question asks for price variance on purchase, and AQ used if it is on consumption. Read the question.
- Material usage variance (MUV)
- MUV = SP × (SQ − AQ)
- AQ here is the quantity actually used. Valued at standard price.
- Material mix variance (MMV)
- MMV = SP × (RSQ − AQ), or Standard cost of standard mix for actual input − Standard cost of actual mix
- RSQ (revised standard quantity) = total actual input × standard proportion of that material. Applies only when two or more materials are used.
- Material yield variance (MYV)
- MYV = SP × (SQ − RSQ), or Standard cost per unit of output × (Actual output − Standard output for actual input)
- Also called sub-usage variance. Adverse when output is lower than the total input should have produced.
- Checks
- MCV = MPV + MUV, and MUV = MMV + MYV
- Use these to verify your answer. Keep the same basis (consumption) for all of them.
- Standard hours for actual output (SH)
- SH = Actual output × Standard hours per unit
- Use actual output, not budgeted output. For several grades, work out SH for each grade.
- Labour cost variance (LCV)
- LCV = (SH × SR) − (Actual hours paid × AR)
- Standard cost of actual output minus actual wages. Positive is F, negative is A.
- Labour rate variance
- (SR − AR) × Actual hours paid
- Use hours paid, not hours worked, because the rate applies to every hour paid.
- Labour efficiency variance
- (SH − Actual hours worked) × SR
- Actual hours worked = hours paid − idle hours. Valued at standard rate.
- Idle time variance
- Idle hours × SR
- Always adverse, because idle hours produce nothing.
- Check relationship
- LCV = Rate variance + Efficiency variance + Idle time variance
- Use this to verify your answer before moving on.
- Labour mix variance
- (Revised standard hours − Actual hours worked) × SR, grade by grade
- Revised standard hours = total actual hours worked × standard proportion of that grade. Also equals standard cost of standard mix minus standard cost of actual mix.
- Labour yield variance
- (SH − Revised standard hours) × SR, grade by grade
- Total can also be worked as (SH total − total actual hours worked) × standard average rate per hour.
- Efficiency split
- Efficiency variance = Mix variance + Yield variance
- Applies when idle time is shown separately and mix and yield use hours worked.
- Standard variable overhead for actual output
- SVO = Standard hours for actual output × Standard rate per hour
- Standard hours for actual output = actual units × standard hours per unit.
- Variable overhead cost variance
- VOCV = Standard variable overhead for actual output − Actual variable overhead
- Positive means Favourable (F), negative means Adverse (A).
- Variable overhead expenditure variance
- VOEV = (Standard rate × Actual hours) − Actual variable overhead
- Also written as (SR − AR) × Actual hours. Use hours actually worked, not paid.
- Variable overhead efficiency variance
- VOEffV = (Standard hours for actual output − Actual hours) × Standard rate
- Fewer actual hours than standard gives Favourable.
- Check
- VOCV = VOEV + VOEffV
- Use this to verify your answer.
- Output basis (when rate is per unit)
- Efficiency = (Actual units − Standard units for actual hours) × Standard overhead rate per unit
- Use this only if the question gives a standard overhead rate per unit and the output expected from the actual hours worked. A higher actual output than standard gives Favourable.
- Standard fixed overhead rate
- Per unit = Budgeted fixed overhead ÷ Budgeted output; Per hour = Budgeted fixed overhead ÷ Budgeted hours
- Use the per hour rate for efficiency, capacity and calendar variances. Use the per unit rate for a quick volume variance.
- Absorbed (standard) fixed overhead
- Standard rate × Actual output (or Standard hours for actual output)
- This is the amount charged to production at standard.
- Fixed overhead cost variance
- Absorbed fixed overhead − Actual fixed overhead
- Positive is F, negative is A. It equals expenditure variance + volume variance.
- Expenditure (budget) variance
- Budgeted fixed overhead − Actual fixed overhead
- Uses the budget for the full period, not a flexed figure, because fixed overhead does not flex.
- Volume variance
- Absorbed fixed overhead − Budgeted fixed overhead = Std rate per unit × (Actual output − Budgeted output)
- It equals efficiency + capacity + calendar variances.
- Efficiency variance
- Std rate per hour × (Standard hours for actual output − Actual hours worked)
- Positive means actual output took fewer hours than standard.
- Capacity variance
- Std rate per hour × (Actual hours worked − Revised budgeted hours)
- Revised budgeted hours = Budgeted hours × Actual days ÷ Budgeted days. If no calendar data is given, use budgeted hours.
- Calendar variance
- Std rate per hour × (Revised budgeted hours − Budgeted hours) = Std rate per day × (Actual days − Budgeted days)
- More working days than budget is F, fewer is A.
- Check relationships
- Volume = Efficiency + Capacity + Calendar; Cost = Expenditure + Volume
- Use these as a quick arithmetic check in the exam.
- Sales Value Variance (turnover)
- (AQ × AP) − (BQ × BP)
- Actual sales minus budgeted sales. Favourable if actual sales are higher. AQ = actual quantity, AP = actual price, BQ = budgeted quantity, BP = budgeted price.
- Sales Price Variance
- (AP − BP) × AQ
- Same in both methods. Favourable if actual price is higher than budgeted price.
- Sales Volume Variance (turnover)
- (AQ − BQ) × BP
- Product by product. Favourable if actual units exceed budgeted units.
- Check: turnover method
- Sales Value Variance = Sales Price Variance + Sales Volume Variance
- Use this to check your answer before moving on.
- Revised Standard Quantity (RSQ)
- RSQ of a product = Total AQ of all products × (BQ of the product ÷ Total BQ)
- Actual total units spread in the budgeted proportion. Needed for mix and quantity.
- Sales Mix Variance (turnover)
- (AQ − RSQ) × BP
- Product by product, then add. Mixed at budgeted price.
- Sales Quantity Variance (turnover)
- (RSQ − BQ) × BP
- Equivalently (Total AQ − Total BQ) × budgeted price per unit of the budget mix. Volume = Mix + Quantity.
- Budgeted margin per unit
- BP − Standard cost per unit
- Used in the margin method for volume, mix and quantity.
- Sales Margin Variance
- Actual profit − Budgeted profit
- Actual profit = AQ × (AP − standard cost). Budgeted profit = BQ × (BP − standard cost).
- Sales Margin Volume Variance
- (AQ − BQ) × budgeted margin per unit
- Price variance (AP − BP) × AQ is unchanged. Margin variance = Price + Volume.
- Sales Margin Mix and Quantity Variances
- Mix = (AQ − RSQ) × budgeted margin per unit; Quantity = (RSQ − BQ) × budgeted margin per unit
- Margin Volume = Mix + Quantity.
- Profit reconciliation
- Actual profit = Standard (budgeted) profit + Favourable variances − Adverse variances
- Use the same costing basis throughout. Check that the closing figure equals the given actual profit.
- Total cost variance
- Cost variance = Standard cost of actual output − Actual cost
- Positive is favourable and negative is adverse. So an adverse variance means Actual cost = Standard cost + the variance amount. For sales and profit, the sign logic is reversed: higher actual gives F.
- Material variances
- MCV = SC − AC; MPV = (SP − AP) × AQ; MUV = (SQ − AQ) × SP; MCV = MPV + MUV
- SQ is the standard quantity for actual output. MUV = Mix variance + Yield variance when there is a mix.
- Labour variances
- LCV = LRV + LEV + Idle time variance; LRV = (SR − AR) × Actual hours paid; LEV = (SH − Actual hours worked) × SR; Idle time variance = Idle hours × SR (always A)
- SH is the standard hours for actual output.
- Variable overhead variances
- VOH cost variance = Standard VOH for actual output − Actual VOH; Expenditure = (Std rate × Actual hours) − Actual VOH; Efficiency = (SH − Actual hours) × Std rate
- Expenditure plus efficiency gives the cost variance.
- Fixed overhead variances
- FOH cost variance = Absorbed FOH − Actual FOH; Expenditure = Budgeted FOH − Actual FOH; Volume = Absorbed FOH − Budgeted FOH
- Cost variance = expenditure + volume. Volume can be split into efficiency, capacity and calendar variances.
- Sales margin variances
- Sales margin variance = Actual profit − Budgeted profit; Price = (AP − SP) × AQ; Volume = (AQ − BQ) × Standard profit per unit
- Price plus volume gives the margin variance. Under the margin method, volume is valued at standard profit per unit.
- Disposal rule of thumb
- Small variance: Costing P&L A/c. Significant variance from wrong standards: prorate to WIP, finished goods and cost of sales. Abnormal variance: P&L A/c
- This is accepted practice, not a fixed formula. State your assumption when the question does not say.
Quick revision
- Variance = difference between standard and actual; mark it Favourable (F) or Adverse (A).
- For costs, actual cost lower than standard is F; for sales and profit, actual higher than standard is F.
- Material Cost Variance = Standard cost for actual output − Actual cost.
- Material Price Variance = Actual Quantity × (Standard Price − Actual Price).
- Material Usage Variance = Standard Price × (Standard Quantity for actual output − Actual Quantity).
- Labour Rate Variance = Actual Hours Paid × (Standard Rate − Actual Rate).
- Labour Efficiency Variance = Standard Rate × (Standard Hours for actual output − Actual Hours Worked).
- Idle Time Variance = Idle Hours × Standard Rate; it is adverse (a loss), shown separately from efficiency variance.
- Fixed Overhead Cost Variance = Absorbed fixed overhead − Actual fixed overhead.
- Fixed Overhead Expenditure Variance = Budgeted fixed overhead − Actual fixed overhead.
- Sales Value (Turnover) Variance = Actual sales − Budgeted sales; split into Sales Price Variance and Sales Volume Variance. Under the margin method, use profit (margin) instead of sales value.
- In reconciliation, the sum of the variances must equal the gap between standard and actual figures; if not, recheck.
Common mistakes
- Calling ideal and current standards the same. Fix: Ideal assumes perfect conditions with no loss. Current is attainable with reasonable effort and allows for normal loss and idle time.
- Ignoring normal loss when fixing standard material quantity. Fix: Divide required output by (1 − normal loss %) to get the input, then price the input.
- Using budgeted quantity instead of standard quantity for actual output Fix: Always start with: actual output × standard input per unit. Write SQ before anything else.
- Getting the sign wrong, especially in price variance Fix: Use the forms SP − AP and SQ − AQ. A positive answer is favourable and a negative answer is adverse. Think in terms of 'should have cost' minus 'did cost'.
- Calculating the rate variance on hours worked instead of hours paid Fix: Remember that you pay for every hour on the clock. Rate variance always uses hours paid.
- Using budgeted output to get standard hours Fix: Underline actual output and use only that for SH.
- Using hours paid instead of hours worked for expenditure variance. Fix: Variable overhead normally uses hours actually worked unless the question says otherwise. Check for idle time.
- Valuing efficiency variance at the actual rate. Fix: Efficiency variance is always at the standard rate.
- Flexing the fixed overhead budget for actual output when finding expenditure variance. Fix: Fixed overhead does not flex. Expenditure = Budgeted FO − Actual FO, using the full period budget.
- Using standard hours for actual output in the capacity variance. Fix: Capacity compares actual hours with revised budgeted hours. Efficiency compares standard hours for actual output with actual hours.
Exam tips
- In theory answers, write each type of standard as a separate point with a one-line definition; this earns step marks.
- For MCQs, link keywords: 'perfect conditions' means ideal, 'not revised' means basic, 'present conditions' means current, 'average over cycle' means normal.
- In setting-standard problems, always show normal loss working separately before pricing material.
- For the comparison question, give at least four points of difference in a two-column style written as lines, with a heading for each.
- Show the overhead rate calculation on its own line; examiners award marks for the rate even if later arithmetic slips.
- Write the formula and the working for each variance, with F or A next to every answer. Step marks are given even if one number goes wrong.
- Read whether the question wants price variance on purchase or on usage. This changes the quantity you use and is a common trap.
- In mix and yield problems, show the RSQ calculation clearly. Check that total RSQ equals total AQ.