Skip to content

FRM Part I · FRM Exam Part I · Interest Rate Futures

A fund manages a $100 million bond portfolio with a modified duration of 7.0. The manager wants to reduce the portfolio duration to 3.0 using futures priced at $125,000 per contract, with a duration of 9.0 for the underlying bond. Which trade achieves the target?

Short about 356 contracts. To cut duration from 7 to 3 the manager needs a duration change of minus 4 on $100 million, divided by the futures value times duration of 1.125 million per contract. That gives roughly negative 355.6, so a short position of 356.

  1. AShort 356 contractsCorrect
  2. BShort 267 contracts
  3. CShort 622 contracts
  4. DLong 356 contracts

Explanation

N = (D* - D) x P / (F x Df) = (3 - 7) x 100,000,000 / (125,000 x 9) = -400,000,000 / 1,125,000 = -355.6, so short about 356. Short 267 uses the target duration of 3 instead of the change in duration. Short 622 uses the full duration of 7, which would take the duration to zero. Long 356 has the wrong sign.

Did you get it right without looking?

One question tells you little. A timed set on Interest Rate Futures shows your real accuracy, how long you take and where you lose marks.

More Interest Rate Futures questions