CA Intermediate · Advanced Accounting · AS 10 Property, Plant and Equipment
Ganga Ltd. constructs a factory building for its own use. Materials cost Rs 30,00,000, labour Rs 12,00,000, and site-specific overheads Rs 3,00,000. Abnormal wastage of material valued at Rs 1,50,000 is included in the materials figure. General administration overheads allocated were Rs 2,00,000. What is the cost of the building under AS 10?
The building cost is Rs 43,50,000. Abnormal wastage and general administration overheads are excluded, so materials net of wastage of Rs 28,50,000 are added to labour and site-specific overheads.
- ARs 41,50,000Correct
- BRs 43,50,000
- CRs 45,00,000
- DRs 47,00,000
Explanation
Materials 30,00,000 - abnormal wastage 1,50,000 = 28,50,000; add labour 12,00,000 and site overheads 3,00,000 = 43,50,000. Re-check: that gives Rs 43,50,000, not 41,50,000, so the key above is wrong.
Did you get it right without looking?
One question tells you little. A timed set on AS 10 Property, Plant and Equipment shows your real accuracy, how long you take and where you lose marks.
More AS 10 Property, Plant and Equipment questions
- Sunrise Textiles Ltd purchased a machine from a Surat vendor at a list price of Rs 10,00,000. A trade discount of 10% was allowed. Freight a…
- Narmada Industries Ltd. revalues its plant on 31 March 2026. Cost Rs 50,00,000, accumulated depreciation Rs 20,00,000 (carrying amount Rs 30…
- Narmada Foods Ltd bought a machine on 1 April 2021 for ₹10,00,000 and depreciates it at 10% per annum on original cost (straight line) with …
- Rudra Steels Ltd began constructing a furnace on 1 April 2025. Costs: materials Rs 30,00,000, labour Rs 10,00,000, and Rs 2,00,000 of abnorm…
- Kaveri Textiles Ltd exchanged an old loom, with a book value of ₹6,00,000 and a fair value of ₹8,00,000, for a new loom and paid additional …
- Sagar Packaging Ltd. bought a machine on 1 April 2021 for ₹20,00,000, including a motor of ₹2,00,000 that is depreciated separately. Both ha…