FRM Part II · FRM Exam Part II · Integrated Risk Management
In a bank's ERM framework, the risk appetite statement is being cascaded. Which sequence best reflects how risk appetite, risk limits and risk monitoring should relate?
The board approves risk appetite first, which sets aggregate tolerance. Management then translates it into limits by risk type and business unit and monitors them, escalating breaches. Building appetite from business-unit limits reverses this top-down logic and weakens board oversight.
- ALimits are set first by business units, and the board then derives appetite from the sum of limits
- BBoard-approved appetite defines aggregate tolerance, which is translated into limits by risk type and business unit, with monitoring and escalation of breachesCorrect
- CMonitoring is performed only after year-end, with appetite revised to match actual results
- DAppetite is set by the risk function alone and is not communicated to business units
Explanation
Under ERM, the board sets risk appetite top-down. This is then cascaded into limits by risk type and unit, and monitored with breach escalation. Deriving appetite from the sum of limits reverses the logic, which makes the first option the key distractor.
Did you get it right without looking?
One question tells you little. A timed set on Integrated Risk Management shows your real accuracy, how long you take and where you lose marks.
More Integrated Risk Management questions
- A bank compares two integration approaches. Approach A aggregates capital top-down across risk types using a fixed correlation matrix. Appro…
- Which of the following is the strongest indicator that a firm's risk culture is sound?
- A bank's risk team aggregates stand-alone economic capital for credit, market and operational risk by simply adding the three figures togeth…
- A bank's three lines of defence model is part of its ERM framework. Which activity belongs to the second line?
- A bank is deciding how to integrate risk types in a single enterprise model. Which is a recognized challenge specific to aggregating market,…
- A bank's ERM team assesses three business units with stand-alone economic capital of 60, 40 and 20 (USD million). The correlation between ea…