FRM Part I · FRM Exam Part I · Modeling Non-Parallel Term Structure Shifts and Hedging
In a principal components analysis (PCA) of historical changes in par or spot rates across the maturity spectrum, the first three components are typically interpreted as which of the following, in order of explanatory power?
The first three principal components of yield curve changes are conventionally interpreted as level, slope and curvature, in that order of explained variance. Level is a roughly parallel shift, slope is steepening or flattening, and curvature is a butterfly movement of the middle relative to the ends.
- ALevel, slope, curvatureCorrect
- BSlope, level, curvature
- CCurvature, level, slope
- DLevel, curvature, slope
Explanation
Empirical PCA of yield curve changes yields a first component that moves all rates in the same direction (level or parallel shift), a second that steepens or flattens the curve (slope), and a third that changes the curvature (butterfly). The other orderings do not match the usual ranking by explained variance.
Did you get it right without looking?
One question tells you little. A timed set on Modeling Non-Parallel Term Structure Shifts and Hedging shows your real accuracy, how long you take and where you lose marks.
More Modeling Non-Parallel Term Structure Shifts and Hedging questions
- A bond portfolio has key rate '01s of USD 150 at the 2-year point and USD 450 at the 10-year point, and no other exposure. A trader wants to…
- A manager holds a bond portfolio with KR01s (gain per 1bp fall) of USD 3,000 at the 2-year and USD 9,000 at the 10-year key rates, and zero …
- A portfolio's key-rate 01s (gain per 1 bp fall in the rate) are $4,000 at 2 years, $6,000 at 5 years and -$3,000 at 10 years. The curve then…
- Why do practitioners often prefer a PCA-based approach over a model with many correlated key-rate shifts when hedging term structure risk?
- Which statement about the principal components extracted from a covariance matrix of yield curve changes is correct?
- A bond portfolio has a DV01 of $42,000. A risk manager hedges with Treasury futures, each with a DV01 of $84, to neutralize parallel yield-c…