ACCA Applied Knowledge · Management Accounting
Behavioural aspects of budgeting: formula sheet
Key formulas
- Goal congruence
- Manager's personal aims = Organisation's aims
- Budgets and reward systems should push managers towards what is best for the whole organisation.
- Budgetary slack
- Slack = Budgeted cost allowance − Cost actually needed
- Slack is deliberately built in by managers. It makes targets easy and wastes resources.
- Motivation rule of thumb
- Best motivation: targets that are challenging but achievable and accepted
- This is a general tendency, not a guaranteed result. Individuals differ.
- Controllability rule
- Judge managers on controllable items only
- Uncontrollable costs should be separated in reports or excluded from the manager's assessment.
- Cost slack
- Cost slack = Budgeted cost − Realistic (needed) cost
- A positive figure means the budget is padded. Use it when the question gives you both figures.
- Revenue slack
- Revenue slack = Realistic revenue − Budgeted revenue
- A positive figure means sales were understated in the budget.
- Slack as a percentage
- Slack % = Slack ÷ Realistic figure × 100
- Divide by the realistic figure, not the padded budget, unless the question says otherwise.
- Ideal standard
- Assumes perfect conditions, no allowance for waste, idle time or breakdowns
- Usually unattainable. Adverse variances are expected, which can demotivate. Useful as a long-term aim.
- Attainable standard
- Efficient working with allowance for normal losses, waste and downtime
- Challenging but achievable. Generally best for motivation.
- Easy (low) standard
- Can be reached with little effort, often based on past performance
- Little motivation to improve. Encourages slack.
- Controllable cost
- A cost a manager can influence by their own decisions in the period
- Judge managers on these. Controllability depends on the manager and time frame.
- Controllable profit (responsibility reporting)
- Controllable profit = Revenue − Controllable costs
- Uncontrollable items such as allocated head office costs are excluded or shown separately.
Quick revision
- A budget can motivate or demotivate, depending on how it is set and used.
- Top-down budgets are set by senior management with little input from managers.
- Participative budgets are set with input from the managers who must meet them.
- Participation can improve commitment, accuracy and motivation, but takes more time.
- Budgetary slack means deliberately overstating costs or understating revenue to make a target easier.
- Slack makes budgets less accurate and can waste resources.
- Targets that are too easy give little motivation; targets that are too hard can lead to giving up.
- A challenging but achievable target is generally best for motivation.
- Managers should be judged on items they can control; uncontrollable items are better reported separately.
- Flexed budgets help make comparisons fairer when activity differs from plan.
- Focus on short-term budget results can cause poor long-term decisions.
Common mistakes
- Saying tougher targets always improve performance. Fix: Remember the target must be achievable and accepted. Very tight targets can demotivate and encourage cheating.
- Saying participation always motivates and has no downside. Fix: Always pair participation with the risk of budgetary slack and possible time cost.
- Mixing up top-down and bottom-up. Fix: Top-down means orders come from the top (imposed). Bottom-up means proposals start with budget holders (participative).
- Saying participation always gives better budgets. Fix: Always give both sides. Participation takes time, allows slack and can produce targets that clash with company goals.
- Saying slack means a budget that is too tight. Fix: Remember slack means looseness. It makes the budget easier to achieve, not harder.
- Treating slack as only an overstatement of costs. Fix: Slack also includes understating revenue or output targets. Check both sides.
- Saying ideal standards are best because they push managers hardest. Fix: Remember that targets seen as impossible reduce effort. Attainable standards are usually best for motivation.
- Saying attainable standards allow no waste. Fix: Ideal means no waste or downtime. Attainable allows normal waste and delays.
- Treating participation as a cure-all with no downsides. Fix: Remember that participation can encourage slack, since managers may pad budgets they helped set.
- Confusing slack with a genuine forecast error. Fix: Slack is deliberate. Look for words such as overstated, cushion or padded.
Exam tips
- Objective questions often describe a behaviour and ask for its cause. Match the behaviour to the budget feature first.
- Know both sides of participation: commitment and better information against slack and time cost.
- Do not choose absolute answers such as 'always' or 'never' unless the scenario clearly supports them.
- For number entry on slack, subtract the cost actually needed from the allowance given.
- In multiple response questions, select exactly the number stated and avoid ticking extra options.
- Read whether the question asks for advantages or disadvantages. Many wrong options are true points about the opposite.
- In multiple response questions, select exactly the number stated. Do not add an extra option that merely sounds sensible.
- Distinguish clearly between true participation and pseudo-participation when a scenario mentions managers being consulted.