Basic variance rule
Variance = Standard (or budget) figure − Actual figure, judged by effect on profit
For costs, actual below standard is F and actual above standard is A.
Revenue variance rule
Actual revenue above standard or budget = F; below = A
The direction is opposite to costs.
Standard cost per unit
Standard cost = Σ (standard quantity × standard price) for each cost element
Covers materials, labour and overheads.
Profit reconciliation
Budgeted profit + Σ F variances − Σ A variances = Actual profit
Check that the closing figure agrees to the actual profit given.
Sales price variance
(Actual price − Standard price) × Actual units sold
Or: Actual revenue − (Actual units × Standard price). Higher actual price is favourable. Same under absorption and marginal costing.
Sales volume profit variance (absorption costing)
(Actual units sold − Budgeted units) × Standard profit per unit
More units than budget is favourable. Standard profit per unit = standard price − standard full absorption cost.
Sales volume contribution variance (marginal costing)
(Actual units sold − Budgeted units) × Standard contribution per unit
Standard contribution per unit = standard price − standard variable cost.
Reconciliation to budget
Budgeted profit + Sales volume variance + Sales price variance + cost variances = Actual profit
Adverse variances are subtracted. Use the profit or contribution basis consistently.
Material price variance
(Standard price × Actual quantity purchased) − Actual cost of that quantity
Positive = favourable, negative = adverse. Equivalent form: (Standard price − Actual price) × Actual quantity. If purchases equal usage, use that quantity. If stock is valued at standard, use the quantity purchased.
Material usage variance
(Standard quantity for actual output − Actual quantity used) × Standard price
Positive = favourable (used less than allowed), negative = adverse.
Standard quantity for actual output
Actual units produced × Standard quantity per unit
Use actual output, not budgeted output.
Total material cost variance
(Standard quantity for actual output × Standard price) − Actual cost
Equals price variance plus usage variance when purchases equal usage.
Labour rate variance
(Actual hours paid × standard rate) − (Actual hours paid × actual rate) = (SR − AR) × actual hours paid
Positive result is favourable; negative is adverse. Use hours paid, which includes idle time.
Labour efficiency variance
(Standard hours for actual output − actual hours worked) × standard rate
Positive is favourable; negative is adverse. Always use the standard rate.
Standard hours for actual output
Actual units produced × standard hours per unit
Use actual output, not budgeted output.
Idle time variance
Idle hours × standard rate (always adverse)
Actual hours paid − actual hours worked = idle hours.
Total labour variance check
Standard labour cost for actual output − actual labour cost = rate + idle time + efficiency variances
Use this to check that your parts add up.
Variable overhead expenditure variance
(Actual hours × standard rate per hour) − actual variable overhead cost
Positive = favourable, negative = adverse. Use hours actually worked (or actual hours for the base used).
Variable overhead efficiency variance
(Standard hours for actual output − actual hours) × standard variable overhead rate per hour
Favourable if actual hours are fewer than standard hours allowed.
Fixed overhead expenditure variance
Budgeted fixed overhead − actual fixed overhead
Favourable if actual spend is below budget. Applies in both marginal and absorption costing.
Standard hours for actual output
Actual units produced × standard hours per unit
Always based on output produced, not budgeted output.
Fixed overhead absorption rate
Budgeted fixed overhead ÷ budgeted activity (units or hours)
Used only in absorption costing. It gives the fixed overhead absorbed into each unit or hour.
Operating statement structure
Budgeted profit ± sales variances ± cost variances = Actual profit
Add favourable (F) variances. Subtract adverse (A) variances. Always check that the total equals actual profit.
Sales price variance
(Actual price − Standard price) × Actual units sold
Positive means favourable. Same under both costing methods.
Sales volume variance (absorption costing)
(Actual units sold − Budgeted units) × Standard profit per unit
More units sold than budgeted is favourable.
Sales volume variance (marginal costing)
(Actual units sold − Budgeted units) × Standard contribution per unit
Use contribution, not profit, because fixed overheads are not in unit cost.
Material and labour variances
Price/rate = (Standard price − Actual price) × Actual quantity. Usage/efficiency = (Standard quantity for actual output − Actual quantity) × Standard price
Standard quantity is flexed to actual output (units produced). Positive is favourable.
Fixed overhead expenditure variance
Budgeted fixed overhead − Actual fixed overhead
Shown under both absorption and marginal costing. Positive is favourable.
Fixed overhead volume variance (absorption costing only)
(Actual units produced − Budgeted units) × Standard fixed overhead per unit
Equals absorbed overhead less budgeted overhead. Not used in marginal costing.
Variance
Variance = Standard (or flexed budget) figure − Actual figure, or the reverse, labelled F or A by effect on profit
Always label by the effect on profit: higher profit is F, lower profit is A.
Variance as a percentage
Variance % = Variance ÷ Standard (or budget) figure × 100
Helps decide whether a variance is significant enough to investigate. Use the same base each period.
Investigation rule of thumb
Investigate if expected benefit of finding and fixing the cause > cost of investigating
This is a guide, not a fixed rule. Also consider trends, controllability and the cost of ignoring it.
Typical linked pairs
Material price (F) ↔ usage (A); labour rate (A) ↔ efficiency (F); sales price (A) ↔ sales volume (F)
These are common patterns, not certainties. The link must be supported by the facts given.

Quick revision

  • A favourable variance increases profit. An adverse variance reduces profit.
  • Variance = difference between actual and standard (or flexed) result. Always compare like with like.
  • Material price variance = (standard price − actual price) × actual quantity purchased or used, depending on when price is recognised.
  • Material usage variance = (standard quantity for actual output − actual quantity) × standard price.
  • Labour rate variance = (standard rate − actual rate) × actual hours paid.
  • Labour efficiency variance = (standard hours for actual output − actual hours worked) × standard rate.
  • Sales price variance = (actual price − standard price) × actual units sold.
  • Sales volume variance in absorption costing uses standard profit per unit. In marginal costing it uses standard contribution per unit.
  • Fixed overhead expenditure variance = budgeted fixed overhead − actual fixed overhead.
  • Operating statement: start with budgeted profit, adjust for each variance, end with actual profit.
  • Variances can be linked. A cheap material may give a favourable price variance but an adverse usage variance.
  • Always flex the budget to actual output before judging cost variances.

Common mistakes

  • Labelling a variance F because the actual number is bigger. Fix: Always ask what happened to profit. Higher cost is A. Higher revenue is F.
  • Adding adverse variances to budgeted profit. Fix: Write F or A beside every figure. Add F and deduct A.
  • Valuing the volume variance at standard selling price. Fix: Volume variance is a profit variance. Use standard profit per unit (absorption) or standard contribution per unit (marginal).
  • Using budgeted units in the price variance. Fix: Price variance always uses actual units sold, because only actual sales were made at the actual price.
  • Using budgeted output instead of actual output to find standard quantity. Fix: Always multiply standard usage per unit by actual units produced.
  • Valuing the usage variance at actual price. Fix: Usage variance is always at standard price. Price effects belong only in the price variance.
  • Using the actual rate to value the efficiency variance. Fix: Efficiency is a quantity variance. Always value hours at the standard rate.
  • Using budgeted output to find standard hours. Fix: Use actual units produced × standard hours per unit.
  • Using standard hours instead of actual hours in the variable overhead expenditure variance. Fix: Expenditure = actual hours × standard rate versus actual cost. Efficiency is the only one that compares standard and actual hours.
  • Using budgeted output to find standard hours. Fix: Always use actual units produced × standard hours per unit for variable overhead efficiency.

Exam tips

  • In objective tests, read the question for the word cost or revenue before you choose F or A.
  • In multiple response questions, select exactly the number asked. Check each option against the profit-effect test.
  • In number entry, include the correct units and enter the figure without the F or A label unless asked.
  • Use the final check on every reconciliation. It catches most sign errors in seconds.
  • In Section B, show the reconciliation in a clear order: budget, variances, actual.
  • Read the costing system in the first sentence. It decides which standard figure you use for volume.
  • Under absorption costing, standard profit per unit equals price minus full standard cost, including fixed overhead.
  • Section A often asks for one variance as number entry. Enter the number only, and check whether the question wants F or A.