Key formulas
- Standard cost per unit
- Standard cost = Σ (standard quantity × standard price) for materials + labour + overheads
- Build the card by adding each element's cost per unit.
- Standard material cost per unit
- Standard kg per unit × standard price per kg
- Standard kg includes normal waste allowance. Price includes carriage inwards and is net of expected discounts.
- Standard labour cost per unit
- Standard hours per unit × standard rate per hour
- Standard hours include allowance for normal idle time and rest.
- Overhead absorption rate
- Budgeted overhead ÷ budgeted activity (labour hours or machine hours)
- Standard overhead per unit = standard hours per unit × this rate.
- Gross input for a given output with normal loss
- Gross input = Net output ÷ (1 − normal loss %)
- Use this to find the standard material quantity per good unit when waste is a percentage of input.
- Types of standard
- Ideal = perfect conditions; Attainable = tough but achievable; Current = present conditions; Basic = unchanged long term
- Ideal standards assume perfect efficiency, so they give a lower standard cost per unit than attainable standards, all else equal. Attainable is the usual recommended basis.
- Direct material cost per unit
- Standard quantity of material × standard price per kg (or per unit)
- Use the quantity needed per finished unit, including normal waste. Do this for each material.
- Direct labour cost per unit
- Standard hours per unit × standard rate per hour
- Do this for each grade of labour. Standard hours include allowance for normal idle time if the question says so.
- Overhead cost per unit
- Standard hours per unit × overhead absorption rate per hour
- Rate = budgeted overhead ÷ budgeted hours (or units). Keep variable and fixed overhead on separate lines.
- Total standard cost per unit
- Materials + Labour + Variable overhead + Fixed overhead (absorption costing)
- Under marginal costing, leave out fixed overhead. The card then shows standard variable cost.
- Standard selling price
- Standard cost + standard profit
- If profit is a margin on selling price: price = cost ÷ (1 − margin %). If a mark-up on cost: price = cost × (1 + mark-up %).
- Normal loss adjustment
- Input needed per good unit = good output required ÷ (1 − normal loss %)
- The loss % is a percentage of input. If the loss is quoted as a percentage of output, multiply instead: output × (1 + loss %).
- Flexed variable cost
- Flexed variable cost = Budgeted variable cost per unit × Actual units
- Use actual units produced for production costs and actual units sold for sales revenue and sales-related costs.
- Flexed fixed cost
- Flexed fixed cost = Original budgeted fixed cost
- Fixed costs are not flexed, assuming activity stays within the relevant range.
- Flexed budget total
- Flexed total cost = Flexed variable cost + Fixed cost
- Do the same for profit: flexed revenue − flexed costs.
- Cost variance
- Variance = Flexed budget cost − Actual cost
- Positive means favourable, negative means adverse. For revenue and profit use Actual − Flexed budget.
- Variable cost per unit
- Variable cost per unit = Budgeted variable cost ÷ Budgeted units
- Needed when the budget gives totals rather than unit costs.
- Variance direction for costs
- Actual cost < standard cost = F; actual cost > standard cost = A
- Lower cost raises profit.
- Variance direction for revenue and profit
- Actual revenue or profit > standard = F; actual < standard = A
- Higher revenue raises profit.
- Reconciliation of profit
- Budgeted profit + Σ favourable variances − Σ adverse variances = Actual profit
- This is the operating statement. Use the same profit basis (standard marginal or absorption) throughout.
- Total cost variance
- Standard cost of actual output − Actual cost
- Positive = F, negative = A. It equals the sum of its price and usage (or rate and efficiency) parts.
- Management by exception
- Investigate only significant variances
- Significance depends on size, trend, controllability and cost of investigating.
Quick revision
- A standard cost is a planned unit cost made of standard quantity and standard price for each input.
- Standards help with planning, control, performance measurement and motivation.
- Standard types include ideal, attainable, current and basic. Attainable standards are usually the most motivating.
- The standard cost card lists each input, its quantity, price and cost per unit, and gives the total.
- A variance is the difference between actual and standard (or flexed budget) results.
- Cost higher than standard is adverse. Cost lower than standard is favourable.
- Revenue or profit higher than standard is favourable. Lower is adverse.
- A fixed budget does not change with activity. A flexed budget is restated for actual output.
- In flexing, variable costs change with output and fixed costs stay the same.
- Always compare actual results with the flexed budget, not the original fixed budget, for cost control.
- Variances should be reported to the manager who can control them, and investigated where they are significant.
- In number entry questions, check units, rounding and whether the sign (A or F) is asked for.
Common mistakes
- Choosing ideal standards as the best basis for motivation. Fix: Remember that ideal standards are almost never met, so they create adverse variances and can demotivate. Attainable standards are usually the best for motivation.
- Adding normal waste as a percentage of output instead of input. Fix: If 10% of input is lost, gross input = net output ÷ 0.90. Read whether the percentage refers to input or output.
- Using the finished output quantity instead of the input quantity when there is normal loss. Fix: Work out the input needed per good unit first, then multiply by the price. The cost of normal loss stays in the unit cost.
- Mixing up mark-up and margin. Fix: Mark-up is on cost: price = cost × (1 + %). Margin is on selling price: price = cost ÷ (1 − %). Read the wording carefully.
- Flexing fixed costs along with variable costs. Fix: Mark each line V or F before you calculate. Only V lines are multiplied by actual units.
- Comparing actual results with the original fixed budget and calling the difference a variance of performance. Fix: Always flex first. The fixed-budget comparison only shows the volume effect mixed with performance.
- Treating a higher actual figure as always adverse. Fix: Ask what it does to profit. Higher revenue is F. Higher cost is A.
- Adding adverse variances to budgeted profit. Fix: Convert each variance to a sign first: F is +, A is −.
Exam tips
- Learn the four standards by their clue words. Questions often describe the standard and ask you to name it.
- Attainable is usually the answer when a question asks which standard best motivates staff.
- In multiple response questions, select exactly the stated number of advantages or disadvantages and watch for statements that fit only unique, non-repetitive output.
- For number entry, work to the decimal places asked and enter the figure without currency signs or commas unless told otherwise.
- Check whether waste is a percentage of input or of output before you calculate.
- Check the first line of the question for marginal or absorption costing before you add anything up.
- Decide whether profit is a mark-up on cost or a margin on selling price. Margin questions need a division, not a multiplication.
- In multiple response questions, check each statement about standards on its own. Typical correct points are that standards are per unit and that normal loss is included.