ACCA Applied Skills · Performance Management
Budgetary systems and types of budget: formula sheet
Key formulas
- Variance
- Variance = Actual result − Budgeted result
- Label each variance as favourable (F) or adverse (A) by its effect on profit. Variance calculations are covered in later topics.
- Budgetary control cycle
- Plan → Record actual → Compare → Investigate variances → Act → Revise
- Control only exists when the comparison leads to action.
- Purposes checklist
- Planning, Coordination, Communication, Motivation, Authorisation, Control, Evaluation
- A memory list for written answers. Use only those relevant to the scenario.
- Production budget (units)
- Sales units + closing inventory of finished goods − opening inventory of finished goods
- Use units, not money. Closing inventory is the target level at the end of the period.
- Material purchases budget (units)
- Material needed for production + closing material inventory − opening material inventory
- Material needed for production = production units × material per unit. Allow for normal losses if told.
- Principal budget factor test
- Compare the maximum activity allowed by sales demand, materials, labour, machine capacity and cash; the lowest is the principal budget factor
- Compare in the same unit, such as units of finished product.
- Order of building budgets
- Principal budget factor budget → other functional budgets → cash budget → master budget (income statement and statement of financial position)
- For most manufacturers the principal budget factor is sales, so the sales budget comes first.
- Incremental budget
- New budget = Previous budget or actual × (1 + expected % change)
- Adjust for inflation and any known volume or policy changes. Check whether the base is last year's budget or actual, as the question states.
- ZBB decision package ranking
- Rank packages by benefit relative to cost; fund from the top until the budget is used
- Minimum-level packages come first. Increments above the minimum are separate packages ranked on their own merit.
- Activity-based budget
- Activity budget = Forecast cost driver volume × Cost per driver unit
- Cost per driver unit = activity cost pool ÷ driver volume. Driver volume comes from planned output.
- Flexed budget cost (variable)
- Flexed variable cost = budgeted variable cost per unit × actual activity
- Use the actual units produced or sold, not budgeted units.
- Flexed budget cost (fixed)
- Flexed fixed cost = original budgeted fixed cost
- Fixed costs do not change within the relevant range.
- Semi-variable cost
- Total cost = fixed element + (variable rate × activity)
- Split the cost first, often using the high-low method, then flex only the variable part.
- Flexed sales revenue
- Flexed revenue = budgeted selling price per unit × actual units sold
- Sales revenue is also flexed to actual volume.
- Variance against flexed budget
- Variance = actual result − flexed budget result
- Label it favourable (F) or adverse (A) based on the effect on profit.
- Imposed (top-down) budget
- Set by senior management → issued to budget holders
- Pros: fast, strategy-aligned, less slack. Cons: low commitment, may be unrealistic, demotivating.
- Participative (bottom-up) budget
- Prepared by budget holders → reviewed and approved by senior management
- Pros: local knowledge, ownership, motivation. Cons: slow, slack, may conflict with strategy.
- Negotiated budget
- Senior management proposal ↔ budget holder proposal → agreed compromise
- Outcome depends on bargaining power. Slack can be challenged but time is needed.
- Budgetary slack
- Slack = budgeted cost − the cost the manager really expects (or the revenue they expect − budgeted revenue)
- Deliberate padding to make targets easier. It is a risk of participation. It distorts resource allocation and variances.
- Budget versus forecast
- Budget = planned target (what we want). Forecast = expected outcome (what we think will happen).
- Use this contrast whenever the question asks for the difference.
- Feed-forward control
- Forecast outcome compared with target, then action taken before the event.
- Feedback control compares actual with plan after the event.
- Beyond budgeting core features
- Rolling forecasts + relative targets + team rewards + flexible resources + devolved decisions
- List these when asked what beyond budgeting replaces the annual budget with.
- High-low variable cost per unit
- Variable cost per unit = (Cost at high activity − Cost at low activity) ÷ (High activity − Low activity)
- Use the highest and lowest activity levels, not the highest and lowest costs. Take the costs that belong to those activity levels.
- High-low fixed cost
- Fixed cost = Total cost at either point − (Variable cost per unit × Activity at that point)
- Check by calculating at the other point. You should get the same fixed cost.
- Regression line
- y = a + bx
- y is the dependent variable (cost or sales), x is the independent variable (activity or time period). b is the slope and a is the intercept.
- Regression slope and intercept
- b = (nΣxy − ΣxΣy) ÷ (nΣx² − (Σx)²); a = (Σy − bΣx) ÷ n
- n is the number of pairs of data. Work out b first, then a.
- Correlation coefficient and coefficient of determination
- r lies between −1 and +1; r² = proportion of the variation in y explained by x
- The closer r is to +1 or −1, the stronger the linear relationship. A value near 0 means a weak linear relationship.
- Time series models
- Additive: Y = T + S + R. Multiplicative: Y = T × S × R
- Y is actual, T is trend, S is seasonal, R is random. Seasonal variations should add to zero (additive) or average 1 (multiplicative) over a full cycle, so adjust the averages if they do not.
- Seasonal variation from the trend
- Additive: S = Actual − Trend. Multiplicative: S = Actual ÷ Trend
- Average the figures for each season over all cycles, then adjust so the total is correct. Forecast = Projected trend + S (additive) or Projected trend × S (multiplicative).
- Learning curve (cumulative average time model)
- Y = aX^b, where b = log r ÷ log 2
- Y is cumulative average time per unit for X units, a is time for the first unit, r is the learning rate as a decimal. For an 80% curve, b ≈ −0.322.
- Total and incremental time
- Total time for X units = X × Y. Time for later units = Total for X units − Total for earlier units
- Always work with totals before subtracting. Never subtract averages.
Quick revision
- Budget purposes: planning, coordination, communication, motivation, control, evaluation and authorisation.
- The principal budget factor is the resource that limits activity, and its budget is prepared first.
- Incremental budgeting adds or subtracts a percentage to last period's figures, so it can carry forward inefficiency.
- Zero-based budgeting starts from nothing and requires every activity to be justified.
- Activity-based budgeting links budgeted costs to the cost drivers of activities.
- A fixed budget does not change with activity, while a flexible budget is adjusted to actual activity.
- Rolling budgets are updated regularly by adding a new period as one expires.
- Participative budgeting involves managers in setting targets and can improve motivation, but may allow budgetary slack.
- Imposed budgets come from the top, are quick to set, and may reduce commitment.
- High-low: variable cost per unit = change in cost ÷ change in activity, using highest and lowest activity levels.
- Learning curve: each time cumulative output doubles, the cumulative average time per unit becomes the learning rate of its previous value. For an 80% rate it becomes 80% of the previous value, a fall of (100% − rate) = 20%.
- Beyond budgeting replaces fixed annual budgets with relative targets and adaptive planning.
Common mistakes
- Listing purposes with no explanation, for example just writing 'planning, control, motivation'. Fix: Add a sentence explaining each purpose and a link to the scenario. Marks are given for explanation and application.
- Confusing coordination with communication. Fix: Coordination means aligning activities so plans fit together. Communication means passing on targets and information. Give a separate example for each.
- Assuming the principal budget factor is always sales demand. Fix: Always compare every constraint in the data. Sales is the factor only if it gives the lowest feasible output.
- Preparing the production budget before the sales budget when sales is the limiting factor. Fix: Begin with the budget for the principal budget factor. Production depends on sales and inventory targets.
- Saying ZBB means every budget is set to zero. Fix: Say it starts from a zero base and requires each activity to be justified. Activities that pass are funded.
- Recommending ZBB for direct production costs. Fix: Link ZBB to discretionary and support costs. Production costs are driven by output, so a justification exercise adds little.
- Flexing fixed costs along with variable costs. Fix: Tick each line as fixed or variable first. Only variable costs change with activity.
- Using budgeted units instead of actual units when flexing. Fix: The flexed budget always uses actual activity. Circle the actual units before you start.
- Treating 'participative' as 'no senior involvement'. Fix: Remember that senior management still reviews and approves a participative budget. The difference is where the first draft comes from.
- Saying slack only exists in imposed budgets. Fix: Slack is padding added by the budget holder. It is mainly a risk of participative and negotiated budgets, because managers have input into the numbers.
Exam tips
- In written answers, tie every purpose to the scenario. Generic lists score poorly.
- Always mention the link between the budget and the organisation's corporate objectives or strategic plan.
- When asked to discuss, include conflicts between purposes, such as control versus motivation, or the risk of budget slack.
- In objective questions, look for the key words in the stem: ahead, aligned departments, permission to spend, target, comparison. They point to the purpose.
- Keep each purpose in a separate short paragraph with a clear heading so the marker can award a mark per point.
- In objective questions, check every constraint before you choose the principal budget factor. Examiners often make sales the obvious answer and hide a lower limit elsewhere.
- Because objective questions are all or nothing, write the units schedule on your scrap paper and check the sign of each inventory change before you answer.
- In written answers, name the stages in order and link each to a purpose: for example, the committee coordinates and the manual standardises the process.