Loan from level instalments (arrears)
L = X × a_n = X × (1 − v^n) ÷ i
i is the effective rate per payment period. v = 1 ÷ (1 + i). First payment one period after the loan.
Level instalment
X = L ÷ a_n
Rearrangement of the equation of value at the loan date.
Interest in an instalment
I_t = i × B_(t−1)
B_(t−1) is the balance just after the previous payment.
Capital in an instalment
C_t = X − I_t
Capital repaid equals the fall in the balance.
Closing balance
B_t = B_(t−1) − C_t = B_(t−1)(1 + i) − X
Use this to roll the schedule forward.
Prospective balance
B_t = X × a_(n−t)
For level instalments in arrears after t payments, with the same i throughout.
Retrospective balance
B_t = L(1 + i)^t − X × s_t
s_t = ((1 + i)^t − 1) ÷ i. Gives the same value as the prospective method.
Capital in the first instalment and growth
C_(t+1) = C_t × (1 + i)
For level instalments in arrears, capital repayments grow geometrically at rate i.
Total interest paid
Total interest = n × X − L
For level instalments with no other charges.
Equation of value for APR
Loan − upfront charges = Σ (payment at time t) × v^t, where v = 1 ÷ (1 + j)
j is the effective rate per payment period. Charges paid later go on the right-hand side as extra payments.
Level instalments
Net amount received = X × a_n at rate j
Use a_n = (1 − vⁿ) ÷ j for payments at the end of each period. Use the annuity-due form if payments start at once.
Periodic rate to APR
APR = (1 + j)^m − 1
m is the number of periods per year. For monthly payments, m = 12.
Nominal to effective
1 + i = (1 + i⁽ᵐ⁾ ÷ m)^m
i⁽ᵐ⁾ is the nominal annual rate convertible m times a year. Use it to compare with the APR.
Flat rate instalment
Instalment = Loan × (1 + flat rate × term in years) ÷ number of instalments
This is only the way the payment is set. The flat rate itself is not the true cost.
Flat rate total interest
I = L × f × n
L is the amount borrowed, f the flat rate per year, n the term in years. Interest is on the original loan throughout.
Level instalment under a flat rate
X = L(1 + f n) ÷ N
N is the total number of payments, for example N = 12n for monthly payments. Payments are equal.
Equation of value for the effective rate
L = X × a(N at j)
Here a(N at j) = (1 − (1 + j)^−N) ÷ j, with payments at the end of each period. Solve for j, the rate per payment period.
Annual effective rate from monthly rate
i = (1 + j)^12 − 1
The nominal rate convertible monthly is i(12) = 12j.
Rough estimate of the nominal rate
r ≈ 2 m I ÷ (P (N + 1))
m is payments per year, I total interest, P the amount borrowed, N total payments. Approximate only, and it tends to overstate. Use it as a starting guess.
Equation of value for a loan
L = Σ Pt × v^t, where v = 1 ÷ (1 + i)
L is the amount borrowed and Pt is the payment at time t. Use the effective rate per payment period.
Level annuity-immediate
aₙ = (1 − vⁿ) ÷ i
Use for n level payments of 1 at the end of each period, valued one period before the first payment.
Increasing annuity-immediate (payments 1, 2, ..., n)
(Ia)ₙ = (äₙ − n × vⁿ) ÷ i
Payment at time t is t. For a different start and step, split into a level part plus an increasing part.
Payments rising in geometric progression
PV = P × Σ for t = 1 to n of (1 + g)^(t−1) × v^t = P × [1 − ((1 + g) ÷ (1 + i))ⁿ] ÷ (i − g)
Valid when i ≠ g. If i = g, PV = n × P ÷ (1 + i).
Balloon payment
B = (L − PV of regular payments) × (1 + i)ⁿ
n is the time of the balloon. The balloon is paid on top of any regular payment due at that time.
Deferred loan
PV at time 0 = v^d × (PV of payments valued at time d)
d is the number of periods the payment stream is shifted back to reach time 0.
Outstanding balance (prospective)
Bt = PV at time t of all future payments, at the loan rate
Right after the payment at time t, exclude that payment.
Outstanding balance (retrospective)
Bt = L × (1 + i)^t − accumulated value of payments made up to t
Gives the same result as the prospective method at the same rate.

Quick revision

  • Equation of value: PV of outflows = PV of inflows at the same rate and date.
  • Any valuation date works. Choose the one that makes the equation simplest.
  • Interest in a payment = rate × opening balance; capital repaid = payment − interest.
  • Outstanding balance prospectively = PV of the remaining payments at the loan rate.
  • Outstanding balance retrospectively = accumulated loan − accumulated payments made.
  • APR is the effective annual rate that equates the amount received with the PV of all payments and charges.
  • Compute APR on the actual cash flows, including fees, not on the quoted rate alone.
  • Flat rate interest is charged on the original loan for the whole term, so the effective rate is higher than the flat rate.
  • Convert nominal rates to effective rates before comparing loans.
  • For early repayment, settle the outstanding balance at that date, plus any stated penalty.
  • Check every schedule: closing balance after the last payment should be zero.
  • Show the equation, the rate, the time point and the result, with units, in every written answer.

Common mistakes

  • Using the annual rate for monthly or half-yearly instalments. Fix: Convert first. For a nominal rate compounded monthly, use i^(12) ÷ 12 per month and count n in months.
  • Calculating interest on the original loan every period. Fix: Interest is always the period rate times the current outstanding balance.
  • Using the full loan as the amount received when a fee is deducted upfront. Fix: Subtract the fee at time 0. The borrower receives less than the loan, but repays on the full loan.
  • Multiplying the monthly rate by 12 and quoting it as the APR. Fix: APR is an effective annual rate. Compute (1 + j)¹² − 1. The product 12j is only the nominal rate convertible monthly.
  • Treating the flat rate as the effective rate Fix: A flat rate is only a way of working out total interest. Always solve the equation of value to get the true rate.
  • Using the wrong number of payments Fix: Set N = payments per year × years. Match the rate j to the same period as the payment.
  • Valuing an annuity at the wrong date, for example using aₙ for a deferred loan without discounting further Fix: State the valuation date of the annuity factor on your timeline. Then discount or accumulate it to the date you need.
  • Forgetting that the balloon is paid in addition to the last regular instalment Fix: Read carefully. If the question says 'in addition', include both at that time. If it says 'the final payment is', it replaces the regular one.

Exam tips

  • Always state the valuation date and write the equation of value in words before the numbers. Examiners give method marks for it.
  • Use the prospective method as your main route. It needs fewer steps. Use the retrospective method only as a check or when asked.
  • Show a short schedule table in written answers and confirm the final balance is zero. This catches errors fast.
  • In computer-based Paper B questions, set the rate per period in a cell, use a formula for X, and fill the schedule down with formulas rather than typed numbers.
  • Read the timing carefully. Arrears versus advance, and a deferred first payment, are the usual traps in MCQs.
  • Write the equation of value in words first, then in symbols. Examiners give marks for the correct setup even if the solving goes wrong.
  • State your time unit and payment timing as assumptions at the start of the written answer.
  • For Paper B, show the formula, the rate you solved for and the conversion step. Do not give only the final APR.