- Five-step model
- Contract → Performance obligations → Transaction price → Allocation → Recognition
- Learn the order. Every Ind AS 115 problem follows this sequence.
- Scope exclusions (para 5)
- Leases (Ind AS 116); insurance contracts (Ind AS 117); financial instruments etc. (Ind AS 109, 110, 111, 27, 28); non-monetary exchanges between entities in the same line of business to facilitate sales to customers
- Everything else with a customer is in scope.
- Performance obligation
- Promise to transfer (a) a distinct good or service (or bundle), or (b) a series of distinct goods or services that are substantially the same with the same pattern of transfer
- Set-up activities that transfer nothing to the customer are not performance obligations.
- Combining contracts (para 17)
- Same customer (or related parties) + at or near the same time + any one of: package with single commercial objective; price depends on the other contract; goods or services form a single performance obligation
- Only one criterion needs to be met.
- Progress measurement (para 39)
- For obligations satisfied over time, measure progress to depict performance in transferring control
- Used in Step 5 for over-time revenue.
- Contract criteria (para 9)
- Approved and committed + rights identifiable + payment terms identifiable + commercial substance + collection probable
- All five must be met. Collectability considers only the customer's ability and intention to pay.
- Separate contract (para 20)
- Added goods/services are distinct AND price rises by stand-alone selling prices (with appropriate adjustments)
- Both conditions are needed. Then the modification is a separate contract and the old contract is unchanged.
- Prospective treatment (para 21(a))
- Remaining consideration = unrecognised consideration of old contract + consideration for the modification
- Used when remaining goods are distinct from those already transferred. Treated as termination of old and creation of new contract.
- Cumulative catch-up (para 21(b))
- Revenue adjustment at modification date = effect on transaction price and on measure of progress
- Used when remaining goods are not distinct and form part of a single partly satisfied performance obligation.
- Combination test (para 17)
- Same customer + at or near same time + (package OR price interdependence OR single performance obligation)
- Any one of the three criteria is enough.
- Cash received, no contract (para 15)
- Revenue only if no remaining obligations and consideration non-refundable, or contract terminated and non-refundable
- Otherwise recognise a liability.
- Performance obligation (para 22)
- Performance obligation = promise to transfer (a) a distinct good/service or bundle, or (b) a series of distinct goods/services that are substantially the same with the same pattern of transfer
- Assess at contract inception. Each such promise is accounted for separately.
- Series conditions (para 23)
- Series = one obligation if (a) each item is satisfied over time AND (b) the same progress measure applies to each item
- Both conditions must be met. Failing either means the items are separate obligations.
- Principal test (B34A, B35)
- Principal = controls the specified good/service before transfer to the customer
- Momentary legal title alone does not prove control. A principal may use a subcontractor.
- Principal revenue (B35B)
- Revenue = gross consideration the entity expects to be entitled to
- Applies when the principal satisfies the performance obligation.
- Agent revenue (B36)
- Revenue = fee or commission, often = consideration received − amount paid to the other party
- An agent does not control the good or service before transfer.
- Expected value
- Expected value = Σ (probability × possible consideration amount)
- Paragraph 53(a). Suits a large number of contracts with similar characteristics.
- Most likely amount
- Most likely amount = single most likely outcome in the range
- Paragraph 53(b). Suits contracts with only two possible outcomes, such as a bonus achieved or not.
- Present value for financing component
- Revenue = Present value of promised consideration at the contract-inception discount rate
- The objective is the cash selling price (paragraph 61). Use the rate of a separate financing transaction and do not update it after inception (paragraph 64).
- Non-cash consideration
- Measure at fair value; if not reasonably estimable, use stand-alone selling price of goods or services promised
- Paragraphs 66 and 67. If fair value varies for reasons other than form, apply the constraint (paragraph 68).
- Consideration payable to a customer
- Transaction price = Contract price − consideration payable to customer (unless for a distinct good or service)
- Paragraphs 70 and 71. If the payment exceeds the fair value of a distinct good or service received, the excess reduces the transaction price. If fair value cannot be reasonably estimated, the whole payment reduces it.
- No significant financing component
- Advance payment with timing at customer's discretion; consideration that is substantially variable on an uncontrollable future event; difference arising for reasons other than finance
- Paragraph 62 lists these three cases.
- Relative SSP allocation
- Amount allocated to an obligation = Transaction price × (SSP of that obligation ÷ Sum of SSPs of all obligations)
- Para 74 and 76. SSP is determined at contract inception for each distinct good or service.
- Discount in a bundle
- Discount = Sum of SSPs − Promised consideration
- Para 81. If positive, the customer has received a bundle discount. Spread it proportionately unless para 82 evidence exists.
- Residual approach
- Estimated SSP = Total transaction price − Sum of observable SSPs of the other items
- Para 79(c). Allowed only if the price is highly variable or uncertain (not yet established and never sold stand-alone).
- Estimation methods for SSP
- Adjusted market assessment | Expected cost plus a margin | Residual approach
- Para 79. The list is illustrative, not exhaustive. Combinations can be used (para 80).
- Single performance obligation
- No allocation needed
- Para 75. Paras 76 to 86 do not apply, except that paras 84 to 86 may apply to a series with variable amounts.
- Timing decision
- Over time if any one criterion in paras 35 to 37 is met; otherwise point in time
- Decide at contract inception for each performance obligation (para 32).
- Output method
- Progress % = value of goods or services transferred to date ÷ total value promised under the contract
- Examples: surveys, appraisals, milestones, time elapsed, units produced or delivered (para B15).
- Cost-based input method
- Progress % = cost incurred to date ÷ total expected cost
- Input methods use efforts such as costs, labour hours, machine hours. Adjust for costs that do not depict performance (para B19).
- Cumulative revenue and period revenue
- Revenue for the period = (Progress % × transaction price) − revenue recognised in earlier periods
- This is the working method used to apply progress; it follows from remeasuring progress each period (para 40).
- Costs excluded from input method
- Exclude wasted costs from significant inefficiencies not reflected in price; exclude uninstalled-goods margin where the B19(b) conditions are met
- For such goods, revenue may equal their cost (para B19(b)).
- Single method rule
- One method per performance obligation, applied consistently, progress remeasured each reporting date
- Para 40.
- Capitalising costs to fulfil (para 95)
- Capitalise only if: (a) directly related to a specific contract + (b) generates or enhances resources for future performance + (c) expected to be recovered
- All three must be met, and the costs must not be within the scope of another Standard (Ind AS 2, 16, 38).
- Incremental cost to obtain a contract
- Capitalise if incremental and expected to be recovered; otherwise expense
- Costs incurred whether or not the contract is won are expensed, unless explicitly chargeable to the customer.
- Practical expedient (para 94)
- Amortisation period ≤ 1 year → may expense incremental costs when incurred
- It is an option, not a requirement. It applies to costs of obtaining a contract.
- Impairment of contract cost asset
- Impairment = Carrying amount of asset − (Remaining consideration expected − Costs still to be incurred)
- Recognised in profit or loss. Impair other-Standard assets first (para 103).
- Contract asset
- Contract asset = Revenue recognised for work done − Amounts billed or unconditionally due
- Applies where the right to payment depends on something other than passage of time.
- Contract liability
- Contract liability = Consideration received or due − Revenue recognised so far
- Shown when the customer has paid (or payment is due) before you perform.
- Key disclosures (paras 116, 118, 127, 128)
- Opening and closing receivables, contract assets, contract liabilities; revenue recognised from opening contract liability; explanation of significant changes; closing balance of cost assets by category; amortisation and impairment for the period
- Para 127 also requires judgements made and the amortisation method.
- Right of return: what to recognise
- Revenue = price × units NOT expected to be returned; Refund liability = price × units expected to be returned; Asset = cost of units expected to be returned (less any recovery cost)
- Cost of sales is reduced for the asset. Update the refund liability at each reporting date; the change goes to revenue.
- Exchange is not a return
- Same type, quality, condition and price exchange → not a return
- Defective-for-working exchanges follow the warranty guidance.
- Warranty test
- Assurance only → not a separate performance obligation; extra service → separate performance obligation
- If both are promised and cannot be separated, treat as one performance obligation.
- Bill-and-hold criteria (all four)
- Substantive reason + separately identified + ready for transfer + no ability to use or redirect
- Plus the control test in paragraph 38. If met, consider custodial obligations and allocate price to them.
- Repurchase forms
- Forward = obligation; Call = right; Put = obligation at customer's request
- Identify the form first, as the accounting depends on it.
- Material right allocation
- Allocate transaction price on relative stand-alone selling prices, including the option
- The option's stand-alone price reflects the discount and the likelihood of exercise.
Quick revision
- The five steps: identify the contract, identify performance obligations, determine the transaction price, allocate the price, recognise revenue as obligations are satisfied.
- The allocation objective (para 73): allocate the price to each performance obligation to depict the consideration the entity expects to be entitled to.
- Allocation is on a relative stand-alone selling price basis (para 74), with separate rules for discounts and for variable consideration.
- If a contract has only one performance obligation, the allocation paragraphs 76 to 86 do not apply (para 75), though 84 to 86 may apply to a series of distinct goods or services with variable amounts.
- Transaction price covers variable consideration, time value of money and non-cash consideration. Variable consideration is estimated and may be constrained.
- Costs to fulfil a contract are capitalised only if outside Ind AS 2, 16 and 38 and they meet all three tests in para 95: directly related, generate or enhance resources, and expected to be recovered.
- Over-time recognition needs a method (output or input) and an explanation of why it faithfully depicts transfer (para 124).
- Disclose opening and closing receivables, contract assets and contract liabilities, and revenue recognised from the opening contract liability (para 116).
- Disclose a reconciliation of revenue to the contracted price, showing each adjustment such as discounts, rebates, refunds and bonuses (para 126AA).
- A practical expedient lets you skip remaining-obligation disclosure for contracts of one year or less (para 121), but you must say whether you use it (para 122).
- Write the conclusion for every judgement: state the test, apply the facts, then give the treatment.
Common mistakes
- Applying Ind AS 115 to lease contracts or financial instruments. Fix: Remember the para 5 exclusions: leases go to Ind AS 116 and financial instruments to Ind AS 109 and related Standards.
- Treating contract set-up work as a separate performance obligation. Fix: Para 25 says set-up activities are not performance obligations unless they transfer a good or service to the customer.
- Treating any modification adding distinct goods as a separate contract. Fix: Also check that the price rise reflects stand-alone selling prices. A discounted add-on beyond appropriate adjustments fails.
- Recognising cash received as revenue when the para 9 criteria fail. Fix: Recognise a liability until a para 15 event occurs, or until the criteria are later met (para 14).
- Treating every item listed in the contract as a separate performance obligation. Fix: Test each item. If it is not distinct from other promises, combine it into a distinct bundle and count that bundle once.
- Deciding principal or agent once for the whole contract. Fix: Paragraph B34 requires the assessment for each specified good or service. Conclude item by item.
- Using the contract price as revenue without checking for discounts, rebates or bonuses. Fix: Scan every clause for amounts that depend on future events and estimate them before totalling.
- Using expected value for a two-outcome bonus. Fix: For a bonus earned or not, the most likely amount is the usual choice under paragraph 53(b). Use expected value for a large portfolio of similar contracts.
- Allocating the entire discount to the main product, or to the item easiest to discount. Fix: Allocate proportionately to all obligations unless the question gives observable evidence that the whole discount relates to specific items (para 81 and 82).
- Allocating the price based on cost or on the invoice split in the contract. Fix: Allocate on relative stand-alone selling prices. Contract prices are used only if they equal the SSP.
Exam tips
- In MCQs, the scope exclusions and the para 17 combination criteria are favourite test points. Learn the exact lists.
- In case-based answers, name each step of the model in your working. Examiners award marks per step.
- Use Ind AS terminology: 'balance sheet' and 'statement of profit and loss'.
- Do not quote a paragraph number unless you are sure. The ones in this page are safe: 5, 17, 25, 39, 113.
- Always end a scenario answer with a clear conclusion on whether, what and when revenue is recognised.
- Write the paragraph number next to each conclusion. It shows the examiner your basis.
- In case scenarios, look for words such as same customer, negotiated together, or discount linked to another contract. They signal combination under para 17.
- For modifications, state both tests of para 20 explicitly before moving to para 21.