NPA test for a term loan
Interest or instalment overdue for more than 90 days ⇒ NPA
Count days from the due date. Overdue for exactly 90 days is not yet an NPA; it must exceed 90 days.
Sub-standard asset
NPA for a period up to 12 months ⇒ Sub-standard
Starts the day the account is classified as NPA.
Doubtful asset
Sub-standard for 12 months ⇒ Doubtful
Further sub-divided by how long it has been doubtful, which matters for provisioning rates.
Loss asset
Loss identified, not fully written off ⇒ Loss
Identified by the bank, internal or external auditors or RBI inspection.
Income recognition on NPA
Interest on NPA = recognised only when actually received
Interest accrued but unrealised is not taken to income; earlier accrued interest is reversed as per RBI norms.
Overall flow
Standard → Sub-standard → Doubtful → Loss
Downgrade is by time in NPA and by deterioration of security.
Standard asset provision
General provision = rate × outstanding standard advances
The rate is 0.40% for most advances. Some sectors have different rates, such as lower for direct agriculture and SMEs and higher for commercial real estate. Use the rate given in the question.
Sub-standard asset provision
15% × secured portion + 25% × unsecured portion
Rates are those usually applied under RBI norms. Some infrastructure loans have a different rate. Unsecured means the part not covered by realisable value of security.
Doubtful asset provision
Secured portion: 25% (up to 1 year), 40% (1 to 3 years), 100% (over 3 years). Unsecured portion: 100%
The period is the time the asset has stayed in the doubtful category, not the age of the loan.
Loss asset provision
100% of outstanding
The asset may also be written off.
Secured and unsecured split
Secured portion = realisable value of security (up to outstanding); Unsecured portion = outstanding − secured portion
Do this split before applying any rate.
Gross NPA ratio
Gross NPA ÷ Gross advances × 100
Uses advances before deducting provisions.
Net NPA and Net NPA ratio
Net NPA = Gross NPA − provisions held; Net NPA ratio = Net NPA ÷ (Gross advances − provisions) × 100
Textbook questions deduct NPA provisions from both numerator and denominator. Follow any definition the question gives.
Provision coverage ratio
Provisions held against NPAs ÷ Gross NPA × 100
A higher ratio means a stronger cushion.
SMA-0
Overdue 1 to 30 days
Principal or interest unpaid for up to 30 days. Asset is still standard.
SMA-1
Overdue 31 to 60 days
Stress is visible. Bank should start corrective action.
SMA-2
Overdue 61 to 90 days
Last stage before NPA. Resolution should be urgent.
NPA trigger
Overdue more than 90 days → NPA
The 90-day rule is the dividing line between SMA and NPA for term loans.
Days past due count
Days past due = Today's date − Due date of the unpaid amount
Count from the due date. Clear the full overdue amount to reset.
Section 9 SARFAESI: ARC measures
Management change or takeover | sale or lease of business | rescheduling of debts | enforcement of security interest | settlement of dues | possession of secured assets | conversion of debt into shares
The seven measures an ARC may provide for asset reconstruction. Under Section 9(3) the ARC acts in accordance with RBI policies and directions.
Section 10(1) SARFAESI: other functions of an ARC
Agent for recovery of dues | manager under Section 13(4)(c) | receiver if appointed by a court or tribunal
Fees for agency and manager roles are mutually agreed. An ARC cannot act as manager if this gives rise to any pecuniary liability.
Section 10(2) SARFAESI: business restriction
No business other than securitisation or asset reconstruction without prior RBI approval
Applies to an ARC with a certificate of registration, save for the functions in Section 10(1). The Explanation says ARC does not include its subsidiary.
OTS recovery comparison
Recovery % = OTS amount ÷ Total dues × 100
Use it to compare an OTS offer with expected recovery from enforcement, after costs and time.
Net write-off loss
Loss to profit and loss = Amount written off − Provision already held
If provision already covers the loan, the write-off has no further profit impact. Write-off does not extinguish the borrower's liability.
CoC approval threshold (Section 30(4))
Approval needs votes ≥ 66% of the voting share of the financial creditors
Earlier it was 75%; the amended text says sixty-six per cent. Only financial creditors vote.
RP's duty on each plan (Section 30(2))
Plan must cover: CIRP costs, operational creditors, dissenting financial creditors, management, implementation, legality, Board requirements
The RP confirms this before presenting the plan to the CoC (Section 30(3)).
Minimum payment to operational creditors (Section 30(2)(b))
Payment ≥ higher of (i) amount they would get in liquidation under Section 53, or (ii) amount they would get if the plan's total distribution were made in the Section 53(1) order of priority
Compute both measures. The higher one is the floor. The plan's offer must be at least that floor.
Minimum payment to dissenting financial creditors
Payment ≥ amount they would get under Section 53(1) in liquidation
Applies to financial creditors who do not vote in favour of the plan. Distribution must be fair and equitable.
Priority of CIRP costs
CIRP costs are paid in priority to other debts of the corporate debtor
Section 30(2)(a).
Resolution applicant's vote (Section 30(5))
May attend the CoC meeting; no vote unless also a financial creditor
Prevents a conflict of interest in voting on its own plan.

Quick revision

  • An NPA is classified by the bank under RBI norms. Recall the exact categories and definitions from your study material.
  • Special mention stages come before NPA status and are meant for early action.
  • Provisioning reduces profit, so higher NPAs weaken profitability and capital.
  • CIRP under Section 10 begins from the date the Adjudicating Authority admits the application.
  • Under Section 10, the Adjudicating Authority decides within 14 days: admit if complete, reject if incomplete.
  • Before rejecting an incomplete application, the applicant gets notice to fix defects within 7 days.
  • A Section 10 application must include a special resolution of shareholders, or approval by at least three-fourths of partners.
  • Section 29A bars a person, or anyone acting jointly or in concert with them, from submitting a resolution plan.
  • Section 29A(a) to (j) covers undischarged insolvents, wilful defaulters, certain NPA holders, convicted persons, disqualified directors and more.
  • For the NPA ground in 29A(c), the account must be an NPA for at least one year before CIRP begins. The person can still be eligible by paying all overdue amounts with interest and charges before submitting the plan.
  • A person with a connected person who is ineligible under clauses (a) to (i) is also ineligible under clause (j).
  • Section 29A(h) applies to a guarantee given to a creditor that has been invoked and remains unpaid in full or part.

Common mistakes

  • Treating an account overdue for exactly 90 days as an NPA. Fix: Write the test as 'overdue for more than 90 days' and check the strict inequality.
  • Counting the 12 months for doubtful from the date of the loan. Fix: Start the clock on the date the account became an NPA, not the sanction date.
  • Applying one rate to the whole outstanding amount Fix: Always compute the secured portion from the realisable value of security first. Apply the lower rate only to that part.
  • Using the wrong doubtful rate Fix: Read how long the asset has been doubtful. Up to 1 year is 25%, 1 to 3 years is 40%, over 3 years is 100% on the secured portion.
  • Treating SMA-2 as an NPA. Fix: An account is an NPA only after more than 90 days overdue. SMA-2 is still standard.
  • Counting days from the date the bank sends a reminder. Fix: Always count from the due date of the unpaid amount.
  • Saying a write-off waives the borrower's debt. Fix: Write-off is a book entry. The borrower still owes the money and the bank can keep pursuing recovery.
  • Confusing a DRT with a Lok Adalat. Fix: A DRT adjudicates a recovery claim and can pass an order. A Lok Adalat works by compromise between the parties.
  • Saying operational creditors vote on the resolution plan. Fix: Under Section 30(4), the plan is approved by a vote of the financial creditors on their voting share. Operational creditors are protected by the minimum-payment rule in Section 30(2)(b), not by a vote on the plan.
  • Quoting the approval threshold as 75%. Fix: The current Section 30(4) text says not less than sixty-six per cent. of voting share.

Exam tips

  • In MCQs, watch the strict wording: 'more than 90 days' versus 'up to 90 days'.
  • Count days carefully using actual month lengths, and always start from the due date.
  • In case scenarios, underline the dates first. Most answers follow from the day-count.
  • Give a reason with every category you name. One line of reasoning earns marks that a bare label does not.
  • Link classification to provisioning only if the question asks. Otherwise keep the answer tight.
  • In numerical questions, show the secured and unsecured split for each account. Marks are given for steps.
  • Learn the doubtful rates by time band: 25%, 40%, 100% on the secured part, and 100% on the unsecured part.
  • Section A MCQs often test the difference between gross and net NPA, or the effect of a higher provision on profit and capital. Read the denominator carefully.