CMA Final · Strategic Cost Management
Quality Cost Management: formula sheet
Key formulas
- Quality of design vs conformance
- Quality of design = how well the specification meets customer needs; Quality of conformance = how closely actual output matches the specification
- A product can conform perfectly to a poor design. Keep both ideas separate in answers.
- Quality control vs quality assurance
- QC = product-oriented, detects defects after or during production; QA = process-oriented, prevents defects
- Use these two words in every comparison answer.
- PDCA cycle
- Plan → Do → Check → Act
- The standard engine of continuous improvement.
- Dimensions of quality (Garvin)
- Performance, Features, Reliability, Conformance, Durability, Serviceability, Aesthetics, Perceived quality
- Eight dimensions. Link each to the product in the case.
- Cost of conformance
- Cost of conformance = Prevention costs + Appraisal costs
- Voluntary spending to achieve quality.
- Cost of non-conformance
- Cost of non-conformance = Internal failure costs + External failure costs
- Loss caused by failing to meet specification.
- Total cost of quality
- COQ = Prevention + Appraisal + Internal failure + External failure
- Equals conformance plus non-conformance costs.
- COQ as a percentage of sales
- COQ % = (Total COQ ÷ Sales) × 100
- Used to compare periods or units. Cost of each category can be shown the same way.
- Classification test
- Stop defect = Prevention; Find defect = Appraisal; Defect found before delivery = Internal failure; Defect found after delivery = External failure
- Use this to tag every item.
- Total cost of quality
- Total COQ = Prevention + Appraisal + Internal failure + External failure
- Conformance = prevention + appraisal. Non-conformance = internal + external failure.
- COQ as percentage of sales
- COQ % = (Category cost ÷ Sales) × 100
- Use the same base (sales or total COQ) for every line in the report. State which base you use.
- Optimum quality level (traditional view)
- Optimum = level where Total COQ is minimum, i.e. where marginal conformance cost = marginal failure cost saved
- Beyond this point extra prevention and appraisal spend exceeds the failure cost it removes.
- Zero-defect view
- Optimum = zero defects (or continuous movement towards it)
- Argued on the basis that failure costs, including hidden ones, are underestimated and prevention gets cheaper.
- Taguchi loss function
- L(x) = k (x − T)²
- x = actual value, T = target, k = constant = cost of loss at specification limit ÷ (limit deviation)². Loss is zero only at target.
- Defects per million opportunities (DPMO)
- DPMO = (Number of defects ÷ (Units × Opportunities per unit)) × 10,00,000
- Use total opportunities for defects, not just units inspected.
- Cumulative percentage (Pareto)
- Cumulative % = Running total of causes ÷ Grand total × 100
- Sort causes in descending order before cumulating.
- Six Sigma project method
- DMAIC = Define → Measure → Analyse → Improve → Control
- Used to improve an existing process.
- PDCA cycle
- Plan → Do → Check → Act (then repeat)
- Continuous loop, not a one-off.
- Six Sigma benchmark
- 3.4 defects per million opportunities
- Conventional figure, which allows for a 1.5 sigma long-term shift.
Quick revision
- Quality cost = cost of conformance plus cost of non-conformance.
- Prevention costs are incurred to stop defects from happening, such as training and process design.
- Appraisal costs are incurred to detect defects, such as inspection and testing.
- Internal failure costs arise when defects are found before delivery, such as scrap and rework.
- External failure costs arise after delivery, such as warranty claims, returns and lost goodwill.
- Prevention and appraisal are the cost of conformance; the two failure types are the cost of non-conformance.
- TQM is a continuous, organisation-wide effort to meet customer needs and reduce defects.
- Higher spending on prevention usually reduces failure costs, but the effect has limits.
- The optimum level is where total quality cost is lowest; some views argue for continuous improvement towards zero defects.
- Always end a quality cost report answer with a clear comment and recommendation.
- Match each tool to its purpose before the exam, as Section A may test recognition.
Common mistakes
- Equating quality with high price or luxury features Fix: Define quality as meeting customer requirements and fitness for use. A low-cost product can be high quality.
- Treating QC and QA as the same thing Fix: State that QC detects defects in output, while QA prevents them through process design. Give one example each.
- Treating inspection of incoming material as prevention. Fix: Inspection and testing find defects, so they are appraisal. Prevention is action taken before or in design of the process.
- Putting rework in appraisal or external failure. Fix: Rework of defects found before dispatch is internal failure. Only defects found after delivery are external failure.
- Classifying inspection of finished goods or testing of incoming material as prevention. Fix: Anything that detects defects is appraisal. Prevention stops defects from arising, such as training, supplier selection, design review and preventive maintenance.
- Putting rework and scrap in external failure. Fix: Rework, scrap and re-inspection before despatch are internal failure. Warranty, returns, complaint handling and recalls are external failure.
- Treating Kaizen and Six Sigma as the same thing. Fix: Kaizen is small, continuous, everyone-involved change. Six Sigma is a specialist-led, data-driven project to cut variation, using DMAIC.
- Not sorting causes in descending order before a Pareto cumulation. Fix: Always rank from largest to smallest first, then compute cumulative percentages.
Exam tips
- Section A MCQs often test matching: a scenario to a TQM principle, or a statement to QC versus QA. Learn the keywords for each.
- In written answers, always apply principles to the case facts. A bare list earns few marks.
- For 'discuss' questions, include both the benefit and a practical difficulty, such as the time and training needed for TQM.
- Use the exact terms: quality of design, quality of conformance, prevention, Kaizen, PDCA.
- Mention the cost link in one line. It connects this topic to cost of quality, which is examined with numbers.
- In MCQs, decide the category by timing: before delivery is internal failure, after delivery is external failure.
- In numericals, show each category total separately before the grand total. Marks are given for the classification.
- Always add a one-line comment, such as the need to increase prevention spend when failure costs dominate.