CMA Final · Strategic Financial Management
Investment Decisions, Project Planning and Control: formula sheet
Key formulas
- Net Present Value (NPV)
- NPV = Σ [Ct ÷ (1 + k)^t] − C0, for t = 1 to n
- Accept if NPV > 0 for an independent project. For mutually exclusive projects of similar scale, choose the highest NPV.
- Payback period
- Payback = Initial investment ÷ Annual cash inflow (for even inflows)
- For uneven inflows, add cumulative inflows until the investment is recovered. It ignores cash flows after payback and, in the simple form, the time value of money.
- Profitability index
- PI = Present value of cash inflows ÷ Initial outlay
- PI > 1 means NPV > 0. Useful for ranking under capital rationing.
- Incremental cash flow rule
- Relevant cash flow = Cash flow with the project − Cash flow without the project
- Include opportunity costs and working capital changes. Exclude sunk costs. Ignore financing flows when discounting at the cost of capital.
- Incremental cash flow
- Incremental cash flow = Cash flows with the project − Cash flows without the project
- Test every item with this. If it does not change because of the project, leave it out.
- Initial outlay
- Initial outlay = Cost of asset + Installation and freight + Increase in working capital − Net proceeds of old asset (if replacing)
- Do not include sunk costs. For a replacement, adjust the old asset's sale proceeds for tax on gain or tax saved on loss.
- Operating cash flow (tax method)
- OCF = (Revenue − Cash operating costs − Depreciation) × (1 − t) + Depreciation
- t is the tax rate. Interest is excluded.
- Shortcut form of OCF
- OCF = (Revenue − Cash operating costs) × (1 − t) + Depreciation × t
- Same answer as above. The second part is the depreciation tax shield.
- Depreciation tax shield
- Tax shield = Depreciation × t
- Applies when the firm has enough taxable profit to use the deduction. Use the depreciation method given in the question.
- Terminal cash flow
- Terminal cash flow = Working capital released + Salvage value − Tax on gain (or + Tax saved on loss)
- Gain or loss = Salvage value − Tax book value of the asset.
- Opportunity cost
- Opportunity cost = Best alternative cash flow forgone, after tax
- Include it as a cost of the project. Example: rent forgone on a space the project will use.
- Change in working capital
- ΔNWC = Increase in current assets − Increase in current liabilities
- Outflow when it rises, inflow when it is released.
- Payback period
- Payback = Years before full recovery + (Unrecovered cost at start of the year ÷ Cash inflow of that year)
- For even inflows: Initial outlay ÷ Annual cash inflow. Undiscounted cash flows.
- Discounted payback
- Same as payback, but use present values: PV of inflow = Cash inflow ÷ (1 + r)^t
- Always at least as long as simple payback for a positive discount rate. Needs a cost of capital.
- ARR
- ARR = Average annual accounting profit after depreciation (and tax) ÷ Investment × 100
- Investment may be the initial or the average investment. Use whichever the question states. Average investment = (Initial cost + Salvage value) ÷ 2.
- Net present value
- NPV = Σ [CFt ÷ (1 + r)^t] − Initial outlay
- Accept if NPV > 0. For mutually exclusive projects choose the highest NPV.
- Internal rate of return
- IRR: the r at which Σ [CFt ÷ (1 + r)^t] = Initial outlay. Interpolation: IRR = Lower rate + [NPV at lower rate ÷ (NPV at lower rate − NPV at higher rate)] × (Higher rate − Lower rate)
- Accept if IRR > cost of capital. For even inflows, outlay ÷ inflow gives the annuity factor to look up in the table.
- Profitability index
- PI = PV of cash inflows ÷ PV of cash outflows = 1 + (NPV ÷ Initial outlay)
- Accept if PI > 1. Useful for ranking under a budget limit.
- MIRR
- MIRR = (Terminal value of inflows ÷ PV of outflows)^(1 ÷ n) − 1, where Terminal value = Σ CFt × (1 + reinvestment rate)^(n − t)
- PV of outflows is at the finance rate (usually the cost of capital). n is the project life in years.
- Crossover (Fisher's) rate
- Rate at which NPV of two projects is equal; solve using the incremental cash flows (A − B) and find the IRR of the difference
- Below this rate, NPV and IRR rankings can conflict. Above it, they agree.
- Profitability index
- PI = PV of cash inflows ÷ Initial outlay = 1 + (NPV ÷ Initial outlay)
- Some books define it as NPV ÷ outlay. Check the question and state your definition. Both give the same ranking.
- Capital rationing objective
- Maximise Σ NPV of selected projects, subject to Σ outlay ≤ budget
- For indivisible projects, test combinations. For divisible projects, rank by PI and part-fund the last project.
- Annuity factor
- PVAF(r, n) = [1 − (1 + r)^(−n)] ÷ r
- Use the table value given in the question if provided.
- Equivalent annual annuity
- EAA = NPV ÷ PVAF(r, n)
- n is the project's own life. Choose the project with the higher EAA.
- Equivalent annual cost
- EAC = PV of all costs ÷ PVAF(r, n)
- Use when projects only have costs. Choose the lower EAC.
- Replacement chain NPV
- Chain NPV = NPV + NPV ÷ (1 + r)^n + NPV ÷ (1 + r)^(2n) + ... over the common life
- Common life is the lowest common multiple of the project lives. Add each repeat's NPV discounted back to today.
- Risk-adjusted discount rate
- RADR = Risk-free rate + Risk premium; NPV = Σ [CFt ÷ (1 + RADR)^t] − Initial outlay
- Use the higher rate for riskier projects. Cash flows are the expected (uncertain) ones.
- Certainty equivalent coefficient
- α(t) = Certain cash flow ÷ Risky expected cash flow
- α lies between 0 and 1. It usually falls for later years as uncertainty grows.
- NPV by certainty equivalent
- NPV = Σ [α(t) × CFt ÷ (1 + Rf)^t] − Initial outlay
- Discount at the risk-free rate only. Using RADR here counts risk twice.
- Expected NPV
- E(NPV) = Σ P(i) × NPV(i)
- P(i) are the probabilities of the scenarios and they must add up to 1.
- Standard deviation of NPV (scenarios)
- σ = √[ Σ P(i) × (NPV(i) − E(NPV))² ]
- Use the NPV of each scenario, not the cash flow.
- Standard deviation of NPV (yearly cash flows, independent)
- σ(NPV) = √[ Σ σt² ÷ (1 + r)^(2t) ]
- Valid when cash flows of different years are independent. Use the risk-free rate unless the question says otherwise.
- Standard deviation of NPV (perfectly correlated)
- σ(NPV) = Σ [ σt ÷ (1 + r)^t ]
- Valid only when cash flows of all years are perfectly correlated.
- Coefficient of variation
- CV = σ ÷ E(NPV)
- Risk per rupee of expected NPV. Compare projects with different sizes. Lower is better. Meaningful only when E(NPV) is positive.
- Probability of NPV below zero (normal assumption)
- Z = (0 − E(NPV)) ÷ σ; read the area from the normal table
- Use only when the question tells you to assume NPV is normally distributed.
- Sensitivity of a variable
- % change that makes NPV zero = NPV ÷ PV of that variable's cash flows × 100
- A smaller percentage means NPV is more sensitive to that variable.
- Decision tree roll-back
- EMV at a chance node = Σ (probability × value of branch); at a decision node choose the highest EMV
- Work from right to left. Deduct outlays on the branch where they occur.
- Initial outlay in replacement
- Cost of new asset − Sale proceeds of old asset − Tax saved on loss on sale (or + Tax payable on gain)
- Add any extra working capital. Use only cash items and the tax effect of the sale.
- Incremental annual cash flow (CFAT)
- (Savings or extra profit before depreciation − Incremental depreciation) × (1 − t) + Incremental depreciation
- The same result: Savings × (1 − t) + Incremental depreciation × t. Here t is the tax rate.
- Replacement NPV
- NPV = PV of incremental CFAT + PV of incremental terminal cash flows − Net initial outlay
- Replace if NPV > 0. For unequal lives, use the equivalent annual approach.
- Post-tax cost of debt
- Kd (post-tax) = Interest rate × (1 − t)
- The usual discount rate in lease versus buy, because lease and loan flows are debt-like.
- Cost of leasing
- PV of rentals × (1 − t)
- Take rentals after tax. Adjust the timing if rentals are paid at the start of the year.
- Cost of buying
- Purchase price − PV of depreciation tax shield (Depreciation × t) − PV of salvage after tax
- Add PV of after-tax maintenance or insurance if the buyer bears them and the lessor does not.
- Net advantage of leasing
- NAL = Net cost of buying − Net cost of leasing
- Lease if NAL > 0. All figures at present value.
- Nominal and real rate
- (1 + nominal rate) = (1 + real rate) × (1 + inflation rate)
- The relation is multiplicative. The simple sum is only an approximation.
- Abandonment rule
- Abandon if Salvage value (after tax) > PV of future cash flows from continuing
- Test it at each possible year-end. Compare at the same date.
- PERT expected time
- te = (to + 4tm + tp) ÷ 6
- to = optimistic, tm = most likely, tp = pessimistic time.
- Activity variance and standard deviation
- σ² = [(tp − to) ÷ 6]²; σ = (tp − to) ÷ 6
- Project variance is the sum of variances of critical-path activities only.
- Project standard deviation
- σ(project) = √Σσ² of critical activities
- Assumes activities are independent.
- Probability of completion by a date
- Z = (Due date − Expected project time) ÷ σ(project)
- Read probability from the normal table.
- Slack / float
- Slack = LST − EST = LFT − EFT
- Critical activities have zero slack.
- Cost overrun
- Cost overrun % = (Actual cost − Budgeted cost) ÷ Budgeted cost × 100
- Time overrun is computed the same way on durations.
- Crash cost per period
- (Crash cost − Normal cost) ÷ (Normal time − Crash time)
- Crash the cheapest critical activity first.
Quick revision
- Use incremental, after-tax cash flows only; ignore sunk costs and allocated overheads that do not change.
- Include opportunity costs and the working capital needed, and recover working capital at the end.
- Do not include interest in project cash flows when discounting at the cost of capital; the rate already reflects financing.
- Depreciation is not a cash flow, but it creates a tax shield: depreciation × tax rate.
- NPV = present value of cash inflows − present value of cash outflows; accept if NPV > 0.
- Accept on IRR if it is higher than the required rate, but check conflicts with NPV for mutually exclusive projects.
- Profitability index = present value of inflows ÷ initial outlay; accept if PI > 1.
- Payback ignores time value and cash flows after the payback period; discounted payback fixes only the first problem.
- When funds are rationed, choose the combination of projects with the highest total NPV within the budget.
- For unequal lives, compare using the equivalent annual approach or a common life, not raw NPV.
- Sensitivity analysis changes one variable at a time; scenario analysis changes several together.
- Post-audit compares actual results with the plan to learn and correct future estimates.
Common mistakes
- Treating capital budgeting as only NPV and IRR calculation. Fix: Always mention identification, screening, appraisal, selection, planning, control and post-audit when the question asks about the process.
- Including sunk costs, such as past feasibility study fees, in project cash flows. Fix: Include only costs that change because of the decision. Include opportunity costs, exclude sunk costs.
- Including sunk costs such as a feasibility study or market survey already paid for Fix: Ask whether the cash changes if you accept or reject. Money already spent does not change, so leave it out.
- Deducting depreciation as a cash cost and not adding it back Fix: Depreciation only reduces tax. Add it back after tax, or use the shortcut: Depreciation × t.
- Treating payback or ARR as a time-value-adjusted measure, or ignoring cash flows after the payback period Fix: State its limits in the answer: no time value, ignores later flows. Use it only as a secondary screen.
- Calculating ARR on cash flow instead of accounting profit Fix: For ARR, deduct depreciation from the cash flow, then tax if stated, to get accounting profit. Check whether investment is initial or average.
- Ranking by PI and stopping, even when projects are indivisible. Fix: With indivisible projects, always check whether another combination uses the budget better and gives a higher total NPV.
- Comparing raw NPVs of projects with different lives. Fix: Whenever mutually exclusive projects have different lives, convert to EAA or use a replacement chain first.
- Discounting certainty equivalent cash flows at the risky rate (RADR). Fix: CE flows already carry the risk adjustment. Discount them at the risk-free rate.
- Taking the average of the cash flows as the answer to a probability question and skipping NPV of each scenario. Fix: Compute NPV for each scenario, then the expected NPV, then the standard deviation of NPV.
Exam tips
- Write the stages in order. Examiners give credit for sequence and for linking each stage to the case facts.
- In MCQs, watch the wording: mutually exclusive, independent and contingent are tested as definitions and as small cases.
- In case answers, mention non-financial appraisal before moving to numbers, then end with a clear recommendation.
- If a question gives sunk costs or allocated overheads, say clearly that they are excluded and why.
- Link control to post-audit when the question asks about the full cycle.
- Start every answer by listing relevant and irrelevant items in one or two lines. Examiners often award marks for correctly excluding sunk costs and interest.
- Show the depreciation tax shield as a separate line. It is easy to check, and it protects your marks if you make an arithmetic slip elsewhere.
- Always put working capital in both Year 0 and the final year. In MCQs, check whether the question says it is recovered.