Fundamentals of Business Laws and Business Communication · Breach of Contract and Remedies for Breach of Contract
Liquidated Damages and Penalty under Section 74 of the Indian Contract Act
Updated 10 October 2026 · Fact-checked
Section 74 of the Indian Contract Act deals with a sum named in a contract as payable on breach. Whether it is called liquidated damages or penalty, the court awards only reasonable compensation, not more than the named amount. The injured party must prove breach, but need not always prove actual loss.
Understand Liquidated Damages and Penalty under Section 74
When people make a contract, they sometimes fix in advance the amount one side will pay if it breaks the contract. For example, a builder agrees to pay ₹10,000 for every week of delay. This is a pre-agreed sum for breach.
Liquidated damages means a genuine pre-estimate of the loss that breach is likely to cause. The parties agree on it because actual loss may be hard to prove later. A penalty is a sum fixed mainly to frighten the other party into performing. It is much larger than any likely loss.
In English law, courts enforce liquidated damages and strike down penalties. Indian law is different. Section 74 removes this sharp line. If a contract names a sum payable on breach, or contains a penalty clause, the party who suffers the breach can receive reasonable compensation from the party who broke the contract. The amount cannot exceed the sum named.
So the named sum works as a ceiling. The court looks at the facts and decides what is reasonable. If the named sum is a fair estimate, the court may award all of it. If it is extravagant, the court awards less. It never awards more than the named amount.
Section 74 applies to any stipulation by way of penalty. It also covers a person who enters into a bond, recognizance or similar instrument for the performance of a public duty or an act in which the public are interested. Such a person is liable for the whole sum named, subject to the same rule of reasonable compensation. Courts have held that where loss is difficult or impossible to prove, the named sum can be treated as a fair estimate. Where the loss can be assessed easily, the claimant is expected to show it. Remember that breach itself must be proved first.
Key formulas to remember
- Core rule of Section 74
- Compensation awarded ≤ amount named in the contract
- The court gives reasonable compensation, and the named sum is only the upper limit.
- Liquidated damages
- Liquidated damages = genuine pre-estimate of likely loss
- Agreed in advance because actual loss is hard to measure.
- Penalty
- Penalty = sum fixed to threaten, out of proportion to likely loss
- In India it is not simply void. Only reasonable compensation is allowed.
- Indian position
- Liquidated damages and penalty → both treated under Section 74 → reasonable compensation
- The label used by the parties does not decide the result.
- Condition for claim
- Breach of contract + named sum in contract → right to reasonable compensation
- Without breach there is no claim.
How to solve Liquidated Damages and Penalty under Section 74 questions
Use this method for any question on a sum named in a contract for breach.
- 1Check whether there is a valid contract and whether a breach has actually happened.
- 2Find the sum named in the contract as payable on breach.
- 3Do not be misled by the words used. 'Penalty' or 'liquidated damages' makes no difference under Section 74.
- 4Ask what loss the breach has caused or was likely to cause, and whether the named sum is reasonable against it.
- 5Apply the rule: the claimant gets reasonable compensation, not more than the named sum.
- 6If a question gives a proved loss below the named sum, take the proved loss as the answer. If the loss is higher, cap it at the named sum. If loss is hard to prove, the named sum may be a fair estimate.
- 7State the final amount and tick the matching option.
Quickest way: Cap and reasonableness check
When to use it: Use for numerical or option-based questions where a named sum and a loss figure are given.
- Underline the named sum and the actual or likely loss.
- Remember the court awards reasonable compensation not exceeding the named sum. If a proved loss is below the named sum, the proved loss is typically the answer in exam problems.
- Eliminate any option above the named sum at once.
- Eliminate options saying the whole clause is void just because it is a penalty.
- If no loss figure is given and loss is hard to prove, the named sum is usually the fair estimate.
Common mistakes in Liquidated Damages and Penalty under Section 74
Saying a penalty clause is always void in India.
Students carry over the English law rule.
Fix: Remember Section 74 gives reasonable compensation up to the named sum for both types of clause.
Awarding more than the named sum when loss is higher.
Students think compensation must match the full loss.
Fix: The named sum is the ceiling. Never go above it under Section 74.
Assuming the full named sum is always payable.
Students treat the clause as a fixed price.
Fix: Only reasonable compensation is payable. The court can award less than the named sum.
Relying on the label in the contract.
The words 'penalty' and 'liquidated damages' look decisive.
Fix: The court looks at substance. Under Section 74 the label does not change the rule.
Ignoring the need for breach.
Students focus only on the clause.
Fix: First confirm that a breach has occurred. No breach, no compensation.
Worked examples
Example 1
Ravi agrees to deliver 500 sewing machines to Meena Traders by 1 March. The contract says he will pay ₹50,000 if he fails to deliver on time. He delivers late, and Meena Traders suffers a proved loss of ₹30,000. How much can Meena Traders recover under Section 74?
Show the solution
- There is a valid contract and a breach by late delivery.
- The named sum is ₹50,000.
- Under Section 74, compensation must be reasonable and cannot exceed ₹50,000.
- The proved loss is ₹30,000, which is below the named sum and is reasonable.
- So the compensation is ₹30,000.
Answer: Meena Traders can recover ₹30,000, the reasonable compensation, which is within the named limit of ₹50,000.
Example 2
A contract between Sunil and Kavita Constructions says that if the builder fails to complete work on time, he will pay ₹2,00,000 as penalty. The work is late, and Sunil proves a loss of ₹3,50,000. What is the maximum Sunil can recover?
Show the solution
- Breach is established by the late completion.
- The named sum is ₹2,00,000, and it is called a penalty.
- The label does not matter. Section 74 applies.
- The loss of ₹3,50,000 is above the named sum.
- Compensation cannot exceed the named sum, so the limit is ₹2,00,000.
Answer: Sunil can recover at most ₹2,00,000. The court will award reasonable compensation up to this limit.
Exam tips
- Look for the phrase 'not exceeding the amount named'. It is the key to most MCQs.
- If an option says the penalty clause is void and nothing is payable, it is usually wrong for Indian law.
- When the question says loss was difficult to prove, the named sum is likely a fair estimate.
- Learn the definitions of liquidated damages and penalty in one line each, since difference-based questions are common.
- Always check that a breach has occurred before choosing a compensation option.
Practice questions from Breach of Contract and Remedies for Breach of Contract
- Anil undertakes to repay Bharat a loan of Rs. 1,000 in five equal monthly instalments. The contract provides that if any instalment is not p…
- Arjun borrows Rs. 10,000 from Bhavna and signs a bond stipulating that on default he must pay interest at 75 per cent per annum from the dat…
- Ravi Traders agrees to sell a unique antique clock to Mehta for Rs. 80,000 but then refuses to deliver it. Which remedy is most suitable if …
- Under the Indian Contract Act, 1872, where a contract names a sum payable on breach and that sum is in the nature of a penalty, what is the …
- Under Section 74 of the Indian Contract Act, 1872, when a contract names a sum payable on breach, the party complaining of the breach can re…
Liquidated Damages and Penalty under Section 74: frequently asked questions
What does Section 74 of the Indian Contract Act say?
It says that when a contract names a sum payable on breach, or has a penalty clause, the injured party gets reasonable compensation from the party in breach. The amount cannot exceed the sum named.
What is the difference between liquidated damages and penalty?
Liquidated damages are a genuine pre-estimate of likely loss. A penalty is a sum fixed to scare the other party into performing and is out of proportion to likely loss. Under Section 74, both lead to reasonable compensation up to the named sum.
Is a penalty clause enforceable in India?
It is enforceable only to the extent of reasonable compensation, not exceeding the named sum. The court may award the full named sum if it is reasonable. It will award less if the sum is extravagant.
Do I have to prove actual loss under Section 74?
Breach must always be proved. Where loss is hard to measure, the named sum may be taken as a fair estimate. Where loss can easily be assessed, the claimant is expected to show it.