Cost Accounting · Contract Costing
How to Prepare a Contract Account in Cost Accounting
Updated 10 October 2026 · Fact-checked
A contract account is a separate account for each contract. You debit materials, wages, direct expenses, plant cost or depreciation, sub-contract and overheads. You credit materials returned, sold or on site, and plant value at site. You add work certified and work uncertified. The balancing figure is the notional profit or loss.
Understand Contract Account and Cost Elements
In contract costing, each contract is a separate cost unit. The work is large, done at the customer's site, and often runs for more than one year. So you open a contract account for every contract and collect all its costs in one place.
Most costs are direct because they are traceable to the site: materials sent to site, wages of site workers, direct expenses, sub-contract charges and the cost of using plant. These are debited straight to the contract account. Indirect costs, such as head office expenses, are charged only if the question says so, usually on a given basis or percentage.
The account has two sides. The debit side shows costs incurred. The credit side shows what is still valuable at the year end or has left the contract: materials returned or sold, closing materials at site, and plant at its written-down value. It also shows the value of work done, split into work certified (approved by the contractee's architect or engineer) and work uncertified (done but not yet approved, valued at cost).
Plant needs care. You can debit the plant at cost and credit its written-down value at the year end. Or you can debit only the depreciation for the period. Both give the same net charge. Depreciation runs from the date the plant reaches the site, so a part-year means a part-year charge.
The balancing figure of the account is the notional profit (or loss) to date. How much of it you take to the profit and loss account is a separate rule, covered under profit on incomplete contracts.
Key rules to remember
- Cost of contract to date
- Total debits − (materials returned, sold and at site + plant at site value)
- If plant is shown as depreciation only, there is no plant credit. Do not deduct plant twice.
- Wages for the year
- Wages paid + outstanding at end − outstanding at start (prepaid: the reverse)
- Apply the same accrual logic to other expenses.
- Plant depreciation (straight line)
- Cost × rate % × months at site ÷ 12
- Use cost, or cost less scrap value, as the question says. Use the written-down value method only if stated.
- Plant written-down value at site
- Cost of plant − depreciation to date
- This is the credit in the contract account when plant is debited at cost.
- Loss or gain on materials sold
- Cost of materials − sale proceeds
- Credit the cost of materials, and debit the loss (or credit the gain) to the contract account.
- Value of work done
- Work certified + work uncertified (at cost)
- Credit side of the contract account.
- Notional profit
- Value of work done + credits (returns, closing stock, plant value) − total debits
- Equals value of work done − cost of contract to date.
How to solve Contract Account and Cost Elements questions
Use this order for any contract account question. It keeps every cost in the right place and stops double counting.
- 1Read the question and note the contract price, start date, year end and what you are asked to find (the account, the notional profit, or the work-in-progress value).
- 2List the debit items: materials (direct and from stores), wages with accruals or prepayments adjusted, direct expenses, sub-contract cost, plant, and any allowed overheads.
- 3Adjust each item for accruals, prepayments and part-year timing. Work out plant depreciation for the months at site.
- 4List the credit items: materials returned, materials sold at cost, closing materials at site, and plant at written-down value (if plant was debited at cost).
- 5Post any loss or gain on materials sold or lost to the debit or credit side.
- 6Add work certified and work uncertified on the credit side. Value uncertified work at cost, unless the question gives another value.
- 7Total both sides. The difference is the notional profit or loss. Show it as the balancing figure and write the total of both sides equal.
- 8Check: value of work done − net cost to date should give the same profit figure.
Quickest way: Net cost method
When to use it: Use when the question asks only for the notional profit or the cost of work done, not the full account layout.
- Add all costs incurred: materials, adjusted wages, direct expenses, sub-contract, any loss on materials, and plant depreciation (not plant cost).
- Subtract materials returned, materials sold at cost and materials at site at the year end.
- This gives the cost of contract to date.
- Subtract the cost of work uncertified to get the cost of work certified.
- Notional profit = work certified − cost of work certified. Cross-check with value of work done − cost to date.
Common mistakes in Contract Account and Cost Elements
Crediting plant at cost, or deducting both depreciation and plant value
Students mix the two plant methods.
Fix: Choose one. Either debit cost and credit WDV at site, or debit only depreciation. Never do both.
Charging a full year's depreciation on plant that arrived mid-year
The rate is given per year and students forget the time at site.
Fix: Multiply by months at site ÷ 12. Write the working under the account.
Ignoring outstanding or prepaid wages and expenses
Students copy the 'paid' figure straight into the account.
Fix: Add outstanding amounts and deduct prepaid ones before posting.
Leaving out closing materials at site
The item sits in a later line of the question.
Fix: Tick off every item in the question. Closing materials always appear on the credit side.
Loading head office overheads when the question does not allow it
Students apply a habit from cost sheets.
Fix: Charge general overheads only if the question gives an amount or a rate. Site overheads are always direct.
Valuing uncertified work at contract price
Students confuse it with certified work.
Fix: Take uncertified work at cost unless told otherwise. Certified work is shown at the certified value.
Worked examples
Example 1
Sai Constructions began a contract of ₹40,00,000 on 1 April 2026. For the year ended 31 March 2027: materials purchased for the site ₹8,00,000; materials from stores ₹1,20,000; materials returned to suppliers ₹20,000; wages paid ₹6,50,000 (₹30,000 outstanding at year end); sub-contract cost ₹3,00,000; direct expenses ₹60,000; site office expenses ₹90,000; head office overheads allocated ₹40,000; plant depreciation for the year ₹50,000; materials at site on 31 March 2027 ₹1,00,000; work certified ₹22,00,000; work uncertified, at cost ₹1,50,000. Prepare the contract account and find the notional profit.
Show the solution
- Debit side: materials purchased ₹8,00,000 + from stores ₹1,20,000 = ₹9,20,000.
- Wages: ₹6,50,000 paid + ₹30,000 outstanding = ₹6,80,000.
- Other debits: sub-contract ₹3,00,000; direct expenses ₹60,000; site office ₹90,000; plant depreciation ₹50,000; head office ₹40,000.
- Total debits = 9,20,000 + 6,80,000 + 3,00,000 + 60,000 + 90,000 + 50,000 + 40,000 = ₹21,40,000.
- Credit side: materials returned ₹20,000; materials at site ₹1,00,000; work certified ₹22,00,000; work uncertified ₹1,50,000. Total = ₹24,70,000.
- Notional profit = 24,70,000 − 21,40,000 = ₹3,30,000 (balancing figure on the debit side).
- Check: cost to date = 21,40,000 − 1,20,000 = ₹20,20,000. Value of work done = 22,00,000 + 1,50,000 = ₹23,50,000. Profit = 23,50,000 − 20,20,000 = ₹3,30,000.
Answer: Total of each side of the contract account is ₹24,70,000. Notional profit is ₹3,30,000.
Example 2
Kaveri Infra took a contract on 1 April 2026. Costs to 31 March 2027: materials sent to site ₹5,00,000; materials costing ₹40,000 were sold on site for ₹35,000; wages paid ₹3,20,000, of which ₹10,000 is prepaid; sub-contract cost ₹2,00,000; direct expenses ₹45,000; plant costing ₹6,00,000 was sent to site on 1 July 2026 and is depreciated at 10% p.a. on cost. At year end: materials at site ₹60,000; work certified ₹9,50,000; work uncertified, at cost ₹70,000. Prepare the contract account (plant at cost and written-down value) and find the notional profit.
Show the solution
- Plant depreciation = 6,00,000 × 10% × 9/12 = ₹45,000, because plant was at site for 9 months (July to March).
- Plant WDV at site = 6,00,000 − 45,000 = ₹5,55,000.
- Wages charged = 3,20,000 − 10,000 prepaid = ₹3,10,000.
- Loss on materials sold = 40,000 − 35,000 = ₹5,000 (debit).
- Debit side: materials 5,00,000 + wages 3,10,000 + sub-contract 2,00,000 + direct expenses 45,000 + plant at cost 6,00,000 + loss on sale 5,000 = ₹16,60,000.
- Credit side before profit: materials sold at cost 40,000 + materials at site 60,000 + plant at site 5,55,000 + work certified 9,50,000 + work uncertified 70,000 = ₹16,75,000.
- Notional profit = 16,75,000 − 16,60,000 = ₹15,000.
- Check: cost to date = 16,60,000 − (40,000 + 60,000 + 5,55,000) = ₹10,05,000. Value of work done = 9,50,000 + 70,000 = ₹10,20,000. Profit = ₹15,000.
Answer: Plant depreciation is ₹45,000, plant WDV is ₹5,55,000, and the notional profit is ₹15,000.
Exam tips
- Draw the two-sided account first and list every item from the question in order. Tick each as you post it.
- Show working notes for depreciation, accrued wages and loss on materials. Step marks are given for them even if the final profit is off.
- State your assumption in one line when the question is silent, such as 'uncertified work valued at cost' or 'no head office overheads charged'.
- Always check the profit with the net cost method. It takes under a minute and catches double counting of plant.
- In MCQs, watch the plant wording: 'plant at cost' versus 'depreciation charged' decides whether a plant credit exists.
Practice questions from Contract Costing
- Materials costing Rs 2,00,000 were sent to a contract site and at the year end Rs 15,000 of materials were lost by theft and Rs 25,000 of ma…
- In contract costing, each contract is treated as a separate cost unit mainly because:
- A contract of ₹80,00,000 is 50% complete. Cost to date is ₹36,00,000, work certified is ₹40,00,000 and work uncertified is carried at cost o…
- Under the usual practice in contract costing, work uncertified is valued at:
- While executing a contract, the contractee orders additional work outside the original scope. The usual accounting treatment in contract cos…
Contract Account and Cost Elements in other exams
The same ground in other exams, if you are preparing for more than one or want another angle on it.
Contract Account and Cost Elements: frequently asked questions
How do I treat plant depreciation in a contract account?
Charge depreciation only for the period the plant is at site, using the given rate and method. Then either debit the plant at cost and credit its written-down value at the year end, or debit only the depreciation. The net effect on cost is the same.
Is the contract account a real account or a cost statement?
It is a cost ledger account kept for each contract. Its balancing figure is notional profit, which is later adjusted by the rules on incomplete contracts before any amount is taken to the profit and loss account.
Are sub-contract costs direct costs of the contract?
Yes. Amounts payable to sub-contractors for work on the site are debited to the contract account. If part of the sub-contractor's work is not yet certified, it may need to be included in uncertified work as per the question.
What happens to materials lost or sold at site?
Credit the contract account with the cost of those materials. Debit any loss, or credit any gain, on the sale to the same account.