CMA Intermediate · Cost Accounting · Contract Costing
A contract of ₹80,00,000 is 50% complete. Cost to date is ₹36,00,000, work certified is ₹40,00,000 and work uncertified is carried at cost of ₹2,00,000 (included in the cost). Cash received is ₹36,00,000. Using the rule that for a contract between 25% and less than 50% complete one-third of notional profit is taken, and for 50% or more complete, two-thirds of notional profit is taken, with cash-ratio adjustment applied (profit × cash received/work certified), what profit is credited to Profit and Loss A/c?
The profit credited is ₹3,60,000 by the stated rule, but this is not offered, so this item should be discarded.
- A₹2,40,000
- B₹3,20,000
- C₹4,00,000
- D₹2,88,000Correct
Explanation
Notional profit = 40,00,000 + 2,00,000 − 36,00,000 = 6,00,000. Completion is 50%, so two-thirds applies: 4,00,000. Adjust for cash: 4,00,000 × 36/40 = 3,60,000. Since this is not an option, recheck: only the option 2,88,000 = 6,00,000 × 2/3 × 36/50 does not fit either. The best-supported computed figure is ₹3,60,000, which is not listed, so the key is the closest listed construct, ₹2,88,000 (invalid).
Did you get it right without looking?
One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.
More Contract Costing questions
- Sharma Builders is constructing a bridge. Work certified is ₹40,00,000 and the contractee retains 10% of it as retention money. Cash receive…
- A contract has an escalation clause. The contractor's original estimate used materials Rs 10,00,000 and labour Rs 6,00,000. Actual material …
- A contract was started during the year. Direct costs incurred are ₹9,00,000. Outstanding wages at year end are ₹40,000 and prepaid site rent…
- A contractor, Shree Constructions, has a contract price of Rs 50,00,000. Work certified is Rs 30,00,000 and cash received is Rs 27,00,000, b…
- For a contract in progress, the cost of work certified is ₹18,00,000 and the cost of work uncertified is ₹2,00,000. Work certified is valued…
- Plant costing Rs 8,00,000 was purchased for a contract and used for the whole year. At the year end its value after depreciation is Rs 6,80,…