CMA Intermediate · Cost Accounting · Contract Costing
In contract costing, each contract is treated as a separate cost unit mainly because:
Each contract is a separate cost unit because it is a large, customer-specific work, normally executed at the customer's site on agreed terms, so its costs and profit must be determined individually rather than pooled with other work.
- AContracts are always completed within one accounting year
- BEach contract is usually undertaken at the customer's site to specific terms and has its own cost and profit determinationCorrect
- CContract costs cannot include any indirect expenses
- DContract work is always carried out in a factory under continuous production
Explanation
A contract is a large, customer-specific job usually done at the site, so cost and profit are tracked for each contract separately. Contracts often run beyond a year, and indirect costs can be attributed, so the other options are wrong.
Did you get it right without looking?
One question tells you little. A timed set on Contract Costing shows your real accuracy, how long you take and where you lose marks.
More Contract Costing questions
- Rao Infra has a contract priced at Rs 80,00,000, with an escalation clause. Work certified is Rs 60,00,000. Escalation of Rs 4,00,000 has be…
- Ind AS 115 (Revenue from Contracts with Customers) is applied to construction contracts by companies following Ind AS. Which statement refle…
- Plant costing Rs 8,00,000 was purchased for a contract and used for the whole year. At the year end its value after depreciation is Rs 6,80,…
- Materials costing Rs 2,00,000 were sent to a contract site and at the year end Rs 15,000 of materials were lost by theft and Rs 25,000 of ma…
- A contract of ₹80,00,000 is 50% complete. Cost to date is ₹36,00,000, work certified is ₹40,00,000 and work uncertified is carried at cost o…
- Under the usual practice in contract costing, work uncertified is valued at: