FRM Part II · FRM Exam Part II · Credit Risk
A bank has a drawn loan of USD 10 million and an undrawn committed credit line of USD 5 million to the same borrower. Historical experience suggests that 60% of the undrawn line is drawn by the time of default. The borrower's PD is 4% and LGD is 50% on the total exposure. What is the expected loss?
Exposure at default includes the drawn balance plus the expected drawn share of the commitment: 10 + 0.6 x 5 = USD 13 million. Expected loss is 4% x 50% x 13 million = USD 260,000. Ignoring the undrawn line or counting it fully is wrong.
- AUSD 200,000
- BUSD 260,000Correct
- CUSD 300,000
- DUSD 260,000 plus an additional charge on the undrawn line of USD 60,000
Explanation
EAD = 10 + 0.6 x 5 = 13 million. EL = 0.04 x 0.50 x 13,000,000 = 260,000. Using only the drawn amount gives 200,000; using the full commitment (15 million) gives 300,000. The additional charge option double counts the undrawn amount.
Did you get it right without looking?
One question tells you little. A timed set on Credit Risk shows your real accuracy, how long you take and where you lose marks.
More Credit Risk questions
- A bank's retail risk team builds a scorecard and wants a single statistic that shows how well the score separates defaulters from non-defaul…
- A bank's credit portfolio has a one-year expected loss of USD 40 million. The 99.9% one-year credit VaR, measured as the worst-case loss qua…
- In a one-factor Gaussian copula (Vasicek) model, a large homogeneous portfolio has a one-year PD of 2% and asset correlation rho = 0.20. The…
- A large homogeneous portfolio has unconditional PD of 2%, LGD of 50%, and exposure of USD 1,000 million. Under the Vasicek model, the condit…
- Under the foundation concepts of credit risk, which event is best described as migration risk rather than default risk?
- A bank validates a rating model with a cumulative accuracy profile. The model's accuracy ratio is 0.60. The ratio is defined as the area bet…