FRM Part II · FRM Exam Part II · Introduction to Credit Risk Modeling and Assessment

A bank has a single loan with exposure at default of $10 million, a one-year probability of default of 2%, and loss given default of 40%. Treating EAD and LGD as fixed, what is the expected loss on the loan?

Expected loss equals probability of default times loss given default times exposure at default. With 2%, 40% and $10 million, the result is $80,000. Ignoring the recovery assumption would overstate the loss at $200,000.

  1. A$80,000Correct
  2. B$200,000
  3. C$400,000
  4. D$800,000

Explanation

EL = PD x LGD x EAD = 0.02 x 0.40 x 10,000,000 = $80,000. Omitting LGD gives $200,000, and omitting PD gives $4 million-based figures; $400,000 would use PD x EAD x 2 incorrectly, and $800,000 is a scaling error.

Did you get it right without looking?

One question tells you little. A timed set on Introduction to Credit Risk Modeling and Assessment shows your real accuracy, how long you take and where you lose marks.

More Introduction to Credit Risk Modeling and Assessment questions