FRM Part II · FRM Exam Part II · Risk Management for Changing Interest Rates: Asset-Liability Management and Duration Techniques
A bank has assets of USD 1,000 million with a modified duration of 4.0 and liabilities of USD 900 million with a modified duration of 3.0. Using the duration gap approach, approximately what is the change in the market value of equity if all yields rise by 50 basis points?
Equity value falls by about USD 6.5 million. Asset dollar duration is 4,000 and liability dollar duration is 2,700, a net 1,300; multiplying by the 0.5 percent yield rise gives a loss of 6.5 million because assets lose more value than liabilities.
- ADecrease of USD 6.5 millionCorrect
- BDecrease of USD 13.0 million
- CIncrease of USD 6.5 million
- DDecrease of USD 5.0 million
Explanation
Change in equity = -(D_A x A - D_L x L) x dy = -(4,000 - 2,700) x 0.005 = -1,300 x 0.005 = -6.5 million. Ignoring the 0.5% scaling (using 1%) gives 13.0. Increase has the wrong sign. Using only the asset effect adjusted incorrectly gives other figures.
Did you get it right without looking?
One question tells you little. A timed set on Risk Management for Changing Interest Rates: Asset-Liability Management and Duration Techniques shows your real accuracy, how long you take and where you lose marks.
More Risk Management for Changing Interest Rates: Asset-Liability Management and Duration Techniques questions
- A bank's one-year cumulative repricing gap is positive: rate-sensitive assets (RSA) exceed rate-sensitive liabilities (RSL) over that horizo…
- A bank's one-year cumulative repricing gap is positive: rate-sensitive assets repricing within one year exceed rate-sensitive liabilities re…
- A bank wants to immunize its equity against small parallel yield changes. Assets are 800 with duration 5.0, and liabilities are 720 with dur…
- A bank has the following balance sheet items repricing within one year: rate-sensitive assets of $420 million and rate-sensitive liabilities…
- A risk manager wants to capture non-parallel yield curve moves in a hedge. Which approach is most appropriate?
- A risk manager criticizes a bank's reliance on a simple repricing gap report as its only interest rate risk measure. Which is the most valid…