FRM Part II · FRM Exam Part II · Capital Planning at Large Bank Holding Companies: Supervisory Expectations and Range of Current Practice
A bank has CET1 capital of USD 50 billion and RWA of USD 500 billion. Under stress, cumulative net losses after revenue are USD 15 billion, planned dividends are USD 5 billion, and RWA stay at USD 500 billion. The bank's internal minimum stress CET1 target is 7%. What is the ending CET1 ratio and does it meet the target?
Ending CET1 is 50 minus 15 minus 5, or 30 billion; divided by 500 billion RWA it is 6.0 percent. That is below the 7 percent target, so the bank fails. Omitting the dividends would wrongly show exactly 7 percent.
- A6.0%, below the targetCorrect
- B6.0%, meets the target
- C7.0%, meets the target
- D8.0%, meets the target
Explanation
Ending CET1 = 50 - 15 - 5 = 30 billion. Ratio = 30/500 = 6.0%, which is below the 7% target. Ignoring dividends gives 7.0%, the common error of leaving planned distributions out of the stress projection.
Did you get it right without looking?
One question tells you little. A timed set on Capital Planning at Large Bank Holding Companies: Supervisory Expectations and Range of Current Practice shows your real accuracy, how long you take and where you lose marks.
More Capital Planning at Large Bank Holding Companies: Supervisory Expectations and Range of Current Practice questions
- Which practice best demonstrates effective governance over a bank's stress testing used in capital planning?
- A bank starts with common equity tier 1 (CET1) capital of USD 60 billion and risk-weighted assets (RWA) of USD 600 billion. Under its stress…
- A bank projects pre-provision net revenue (PPNR) under stress using a model fitted to the last eight years of data, which contained no sever…
- Which of the following best describes the role of internal audit in a bank holding company's capital planning process?
- A large bank holding company's capital planning team is projecting losses on its commercial real estate loan portfolio under a supervisory s…
- During an internal audit of a bank holding company's capital planning, the auditor finds that the model used to project pre-provision net re…