CMA Final · Risk Management in Banking and Insurance · Introduction to Risk Management
A bank holds a Rs 200 crore portfolio with a one-year probability of default of 2%, loss given default of 45% and exposure at default equal to the full portfolio value. What is the expected loss on the portfolio?
Expected loss equals probability of default times loss given default times exposure at default, so 2% x 45% x Rs 200 crore gives Rs 1.80 crore. Ignoring loss given default would wrongly give Rs 4 crore.
- ARs 1.80 croreCorrect
- BRs 4.00 crore
- CRs 0.90 crore
- DRs 9.00 crore
Explanation
Expected loss = PD x LGD x EAD = 0.02 x 0.45 x 200 = Rs 1.80 crore. Rs 4.00 crore ignores LGD (0.02 x 200). Rs 0.90 crore is wrong because it multiplies PD by LGD and then by 100 instead of 200.
Did you get it right without looking?
One question tells you little. A timed set on Introduction to Risk Management shows your real accuracy, how long you take and where you lose marks.
More Introduction to Risk Management questions
- A bank's payment system fails for several hours because of a software glitch, and customers incur penalties for delayed transfers which the …
- A bank's net interest income over the next year is being assessed using a repricing gap. Rate-sensitive assets within one year are Rs 600 cr…
- A bank grants a 5-year fixed-rate loan funded by 3-month deposits. If deposit rates rise sharply after a few months, the bank's net interest…
- Which statement best describes liquidity risk in a bank?
- A bank's treasury holds a large portfolio of government securities. Following a sudden rise in market yields, the market value of the portfo…
- A bank's one-day 99% Value at Risk (VaR) on its trading portfolio is Rs 4 crore. Using the square-root-of-time rule and assuming 25 trading …