FRM Part II · FRM Exam Part II · Risk Reporting
A bank reports operational loss events to its risk committee each month. Over 12 months the counts were 4, 6, 5, 3, 7, 5, 4, 6, 5, 5, 4, 6. The reporting team proposes an amber threshold at the mean monthly count plus one sample standard deviation. Month 13 has 8 events. Which statement is correct? (Sum of squared deviations is 16.)
The mean monthly count is 5 and the sample standard deviation is sqrt(16/11), about 1.21, giving an amber threshold near 6.21. Month 13 with 8 events exceeds it, so the amber threshold is breached and should be escalated in the report.
- AThe mean is 5, the sample standard deviation is about 1.21, threshold about 6.21, so month 13 breaches amberCorrect
- BThe mean is 5, the sample standard deviation is about 1.21, threshold about 6.21, so month 13 does not breach
- CThe mean is 5, the standard deviation is 1.33, threshold 6.33, so month 13 does not breach
- DThe mean is 5.5, threshold about 6.7, so month 13 breaches
Explanation
Sum of counts is 60, so mean is 5. Given sum of squared deviations 16, sample variance is 16/11 = 1.4545 and standard deviation about 1.206. Threshold is about 6.21. Eight exceeds it, so amber is breached. Option 2 reaches the wrong conclusion, and 1.33 would be an incorrect standard deviation (it is sqrt(16/9)).
Did you get it right without looking?
One question tells you little. A timed set on Risk Reporting shows your real accuracy, how long you take and where you lose marks.
More Risk Reporting questions
- A bank sets a reporting escalation protocol: any single operational loss event above USD 500,000 must reach the CRO within 24 hours; the mon…
- A bank sets a tolerance for its payments service of a maximum tolerable disruption of 4 hours. After a vendor outage, the service was unavai…
- An operational risk report shows a key risk indicator (KRI) for unreconciled payment items at 480 items against an amber threshold of 400 an…
- A bank's risk function states that its risk data aggregation is 'accurate' because the numbers match the general ledger at quarter-end. Howe…
- An operational risk manager notices that business units submit risk and control self-assessment results that are consistently rated green, w…
- A bank's data governance review of its risk reporting finds the following: the Chief Data Officer owns a central data warehouse, but busines…