FRM Part II · FRM Exam Part II · Backtesting VaR

A bank's 99% one-day VaR backtest over 250 days gives 3 exceptions, below the expected 2.5 only slightly above, yet the desk's average exceedance loss is 4 times VaR, and the largest is 9 times VaR. A validator concludes the model passes the exception count test. Which is the best assessment?

The model likely understates tail severity. Although the exception count is acceptable, losses of four to nine times VaR show extremely fat tails that count-based tests ignore. The validator should examine the tail, for example with extreme value methods, expected shortfall and stress tests, rather than rely on the count alone.

  1. AThe model is adequate because the count is acceptable and magnitude is irrelevant
  2. BThe model likely understates tail severity, so the exception count alone is insufficient and the tail distribution (for example via extreme value methods) should be examinedCorrect
  3. CThe model overstates risk and the confidence level should be raised
  4. DThe exceptions are due solely to weekend effects

Explanation

Count-based tests ignore size. Exceedances of 4 to 9 times VaR indicate very fat tails beyond the quantile, which VaR cannot reveal. Improvements include expected shortfall analysis, stress testing, and modeling the tail with extreme value theory. Passing the count does not make the model adequate for tail risk.

Did you get it right without looking?

One question tells you little. A timed set on Backtesting VaR shows your real accuracy, how long you take and where you lose marks.

More Backtesting VaR questions