FRM Part II · FRM Exam Part II · Backtesting VaR
A bank's 99% one-day VaR model produced 6 exceptions over 250 days. Management argues that, because the model sits in the yellow zone, the supervisor must apply a higher multiplier. Which description of the supervisory treatment within the yellow zone is most accurate?
In the yellow zone the supervisor has discretion over the multiplier increment, guided by the cause of the exceptions. Model integrity problems or poor accuracy support an increase, while bad luck or intraday trading effects may not. Only red-zone results trigger an automatic increase.
- AThe increase is automatic and rises mechanically with each exception count
- BThe supervisor has discretion on the increment, depending on why the exceptions occurred, such as basic integrity of the model or bad luckCorrect
- CThe increase is waived if the exceptions occurred on consecutive days
- DThe multiplier is reset to 3.0 once the bank provides a written explanation for each exception
Explanation
In the yellow zone, the Basel guidance gives supervisors discretion: an increment is possible, and the decision depends on the cause. Causes such as a basic integrity problem in the model or deficient accuracy warrant an increase, whereas bad luck or intraday trading may justify less. Automatic increases apply to the red zone, and clustering or written explanations do not waive the framework.
Did you get it right without looking?
One question tells you little. A timed set on Backtesting VaR shows your real accuracy, how long you take and where you lose marks.
More Backtesting VaR questions
- A regulator and a bank's internal model validation team both use backtesting but with different emphases. Which description most accurately …
- A bank's 10-day 99% VaR is $20 million, and its supervisor sets the multiplier at 3.5 because of yellow-zone backtesting results. Ignoring o…
- A bank has 8 exceptions in the last 250 days under its 99% one-day VaR. Investigation shows the exceptions arose because the model's positio…
- A bank backtests a 95% VaR model. The conditional coverage statistic LR_cc is computed as LR_uc = 1.20 plus LR_ind = 4.10. Under the null hy…
- A risk team finds that its 99% VaR model, truly producing a 3% exception rate, passes the backtest in most 250-day samples. Which statement …
- A risk manager backtests a 99% one-day VaR model over 250 days and wants to test both the correct number of exceptions and whether exception…