FRM Part II · FRM Exam Part II · Basel III: Finalising Post-crisis Reforms
A bank's average annual operational losses over the last ten years are 30 million euros. Its BIC is 100 million euros. The ILM formula is ILM = ln(exp(1) - 1 + (LC/BIC)^0.8), where LC (Loss Component) = 15 x average annual losses. Which is closest to the bank's ILM and resulting operational risk capital?
The Loss Component is 450 million euros, so LC/BIC is 4.5. Raising to 0.8 gives about 3.33, adding 1.718 gives about 5.05, and the natural log is about 1.62 to 1.69. Capital is therefore roughly 160 to 170 million euros, above the BIC, because losses are heavy.
- AILM about 1.0; capital about 100 million euros
- BILM about 1.69; capital about 169 million eurosCorrect
- CILM about 1.69; capital about 16.9 million euros
- DILM about 4.5; capital about 450 million euros
Explanation
LC = 15 x 30 = 450. LC/BIC = 4.5. 4.5^0.8 = exp(0.8 x ln 4.5) = exp(0.8 x 1.504) = exp(1.203) = 3.33. Add e - 1 = 1.718 gives 5.05. ln(5.05) = 1.62, so ILM is about 1.62 to 1.7, i.e. roughly 1.6-1.7, and capital = 100 x 1.62 = about 162-169 million euros. Option 4.5 uses the unadjusted ratio, and the 16.9 million option mis-scales.
Did you get it right without looking?
One question tells you little. A timed set on Basel III: Finalising Post-crisis Reforms shows your real accuracy, how long you take and where you lose marks.
More Basel III: Finalising Post-crisis Reforms questions
- A bank's total risk-weighted assets under its internal models are 600 (in USD million), while the standardised approaches applied to the sam…
- A bank has a USD 10 million off-balance-sheet commitment to a corporate that is unconditionally cancellable at any time without prior notice…
- Under the finalised Basel III operational risk framework, which statement about national supervisory discretion over the Internal Loss Multi…
- Which of the following changes is part of the Basel III finalisation package regarding the use of internal models for credit risk?
- A bank's operational risk loss data governance review finds that a 4 million euro loss was recorded under the business unit that booked the …
- A regulator reviews which components of the Basel III finalisation package changed the framework for operational risk and credit risk. Which…