FRM Part II · FRM Exam Part II · Introduction to Operational Risk and Resilience

A bank's Business Indicator Component is EUR 2.0 billion and its Internal Loss Multiplier is calculated at 0.8 because of a very favourable loss history. Which statement about the capital outcome under the Basel III standardised approach is correct?

Capital is EUR 1.6 billion. Under the standardised approach, capital equals the BIC times the ILM, so 2.0 billion multiplied by 0.8 gives 1.6 billion. An ILM below one reflects relatively low historical losses and reduces the requirement.

  1. ACapital is EUR 2.0 billion because the ILM is fixed at 1 for all banks
  2. BCapital is EUR 1.6 billion, since the ILM scales BIC to reflect lower-than-average historical lossesCorrect
  3. CCapital is EUR 2.8 billion, since ILM is added to BIC
  4. DCapital is EUR 1.6 billion only if the bank uses an internal model

Explanation

Capital = BIC x ILM = 2.0 x 0.8 = EUR 1.6 billion. An ILM below 1 arises when historical losses are low relative to the BIC, and it reduces capital. The ILM is not fixed at 1 (that is a national discretion choice, which this scenario does not assume) and is not additive.

Did you get it right without looking?

One question tells you little. A timed set on Introduction to Operational Risk and Resilience shows your real accuracy, how long you take and where you lose marks.

More Introduction to Operational Risk and Resilience questions