FRM Part II · FRM Exam Part II · Capital Structure in Banks
A bank's Corporate unit has net income after expected losses of 60 million, and is allocated economic capital of 400 million. The bank's cost of equity (hurdle rate) is 12%. Capital earns a risk-free return of 3% that is credited to the unit, adding to income in a RAROC calculation. Using RAROC = (net income after expected loss + return on allocated capital) / economic capital, what are RAROC and the economic value added (RAROC minus hurdle, times capital)?
RAROC is 18% and EVA is 24 million. The 3% credit on 400 million of capital adds 12 million to the 60 million income, giving 72 million over 400 million capital. Excess over the 12% hurdle is 6%, times 400 million, equals 24 million.
- ARAROC 18.0%; EVA 24 millionCorrect
- BRAROC 15.0%; EVA 12 million
- CRAROC 15.0%; EVA 60 million
- DRAROC 18.0%; EVA 72 million
Explanation
Return on capital = 3% x 400 = 12 million. Numerator = 60 + 12 = 72 million. RAROC = 72/400 = 18%. EVA = (18% - 12%) x 400 = 24 million. Ignoring the capital benefit gives 15% and 12 million; 72 million confuses the numerator with EVA.
Did you get it right without looking?
One question tells you little. A timed set on Capital Structure in Banks shows your real accuracy, how long you take and where you lose marks.
More Capital Structure in Banks questions
- A bank's risk committee compares two business units. Unit A earns a net profit of USD 24 million using economic capital of USD 150 million. …
- A bank holds assets of 200 and is funded by 180 of liabilities and 20 of equity. Its pre-tax return on assets is 5% and its pre-tax cost of …
- A bank must hold a 4.5% CET1 minimum, a 2.5% capital conservation buffer, a 1.0% G-SIB surcharge, and a 1.0% countercyclical buffer. Its CET…
- Which factor is most likely to cause a bank's observed optimal capital structure to include much higher leverage than an otherwise identical…
- A bank has equity of $8 billion and total assets of $100 billion. Its assets suffer an unexpected loss of 5% of their value with no change i…
- A risk manager reviews a proposed AT1 instrument. Which feature would cause the instrument to FAIL Basel III criteria for inclusion in Addit…