A bank's internal audit reviews its CFP and finds that the crisis team members' contact lists are current, but no simulation involving the board, treasury, legal and communications has been run in three years. Which finding is most appropriate?
The appropriate finding is that the plan has a testing deficiency. Regular cross-functional simulations are needed to confirm that roles, decision-making speed and communications actually work under pressure. Current contact lists alone do not prove the plan is operational, and testing should not wait for a ratio breach.
- ANo issue, because current contact lists are sufficient evidence that the plan is operational
- BThe plan is deficient in testing; regular exercises across functions are needed to confirm roles, decision speed and communication work in practiceCorrect
- CThe plan should be replaced by relying on central bank facilities, which removes the need for testing
- DTesting is only needed if the bank's liquidity coverage ratio falls below the regulatory minimum
Explanation
A CFP must be tested to verify that roles, escalation and communications function under pressure. Contact lists alone do not show this. Central bank reliance is not a substitute, and testing should not depend on a ratio breach.
Did you get it right without looking?
One question tells you little. A timed set on Contingency Funding Planning shows your real accuracy, how long you take and where you lose marks.
More Contingency Funding Planning questions
- A mid-sized bank is drafting its contingency funding plan (CFP). The Treasurer proposes that, during a liquidity stress event, decision auth…
- A bank's CFP has detailed stress scenarios and a list of contingent funding sources, but it does not name who convenes the crisis team, who …
- A bank's liquidity risk manager is deciding how to link early warning indicators (EWIs) to the CFP. Which approach is most consistent with s…
- Which of the following is the best example of an external early warning indicator of a potential institution-specific liquidity stress event…
- A bank's CFP uses early warning indicators with a two-tier escalation: amber triggers heightened monitoring by the Asset-Liability Committee…
- Which of the following best distinguishes a contingency funding plan from the bank's day-to-day liquidity management?