FRM Part II · FRM Exam Part II · Risk Measurement and Assessment
A bank's operational risk team is setting up an internal loss data collection process. Which design choice best supports the use of the data in operational risk measurement and capital modeling?
The best design records gross losses, recoveries, dates and business line using a consistent taxonomy. This lets the bank model frequency and severity, aggregate across units and analyze recoveries, whereas high thresholds or unit-specific categories lose information or prevent comparison.
- ARecord only losses above a very high threshold to keep the database small and focused on tail events
- BRecord gross loss amounts, recoveries, event dates and business line classification using a consistent taxonomyCorrect
- CRecord losses only when they are fully settled in the general ledger, ignoring dates of discovery and occurrence
- DAllow each business unit to define its own loss categories to reflect local practice
Explanation
Useful loss data needs consistent classification and the gross loss, recoveries and key dates so that frequency and severity can be modeled and recoveries understood. A very high threshold discards information needed for frequency and body-of-distribution estimation. Unit-specific taxonomies prevent aggregation and comparison.
Did you get it right without looking?
One question tells you little. A timed set on Risk Measurement and Assessment shows your real accuracy, how long you take and where you lose marks.
More Risk Measurement and Assessment questions
- A bank wants its risk identification process to capture emerging risks that have not yet produced losses, such as a new payments platform wi…
- A bank's scenario analysis workshop asks business experts for the frequency and severity of a cyber-extortion event. The first estimate give…
- A bank's LDA model for one risk category has an expected annual loss of USD 20 million and a 99.9% annual aggregate loss quantile of USD 260…
- A bank aggregates RCSA results across 40 business units to prioritize remediation. Unit A rates a risk 'high' on a 3-level scale (low, mediu…
- A risk manager notes that key risk indicator (KRI) data for a payments process are manually compiled by the process owners whose performance…
- A bank scores each RCSA risk on a 1-5 scale for likelihood and a 1-5 scale for impact, and defines the risk score as likelihood multiplied b…