FRM Part II · FRM Exam Part II · Guidance on Managing Outsourcing Risk
A bank's senior management is approving a new outsourcing of cloud data hosting for its risk systems. Which sequence of management activities best reflects the risk management life cycle described in the guidance?
The correct sequence is risk assessment, then due diligence in selecting the provider, then contract negotiation, then ongoing monitoring, and finally termination planning. Management must decide whether outsourcing is appropriate and vet the provider before binding the bank to contractual terms and monitoring.
- AContract negotiation, risk assessment, due diligence, monitoring, termination planning
- BRisk assessment, due diligence in selecting the provider, contract negotiation, ongoing monitoring, and termination planningCorrect
- CDue diligence, ongoing monitoring, risk assessment, contract negotiation, termination planning
- DContract negotiation, ongoing monitoring, due diligence, risk assessment, termination planning
Explanation
The life cycle begins with assessing whether and how to outsource (risk assessment), then selecting the provider via due diligence, negotiating the contract, monitoring on an ongoing basis, and planning for termination or exit. The other orders place contracts or monitoring before the decision and selection work, which is illogical.
Did you get it right without looking?
One question tells you little. A timed set on Guidance on Managing Outsourcing Risk shows your real accuracy, how long you take and where you lose marks.
More Guidance on Managing Outsourcing Risk questions
- A bank relies on an outsourced data-center provider for a critical trading platform. The bank's business impact analysis sets a maximum tole…
- A bank outsources 60% of a critical function to Provider A and 40% to Provider B. Both providers use the same cloud infrastructure vendor, w…
- A bank outsources a critical function to a provider that itself relies on a subcontractor (a fourth party). Which action best addresses the …
- A bank's risk committee reviews its critical outsourcing arrangements. A provider's monthly reports show all KPIs green, but the bank has ne…
- A bank's vendor risk team reviews a critical cloud provider. Monthly service level reports show 99.95% availability against a 99.9% target, …
- A bank uses 40 critical outsourced services. Monitoring intensity is set by a score: Tier 1 (score above 80) is reviewed quarterly, Tier 2 (…