FRM Part II · FRM Exam Part II · Case Study: Cyberthreats and Information Security Risks
A bank's threat intelligence unit reports that a criminal group compromised a small software vendor and pushed a malicious update that was then installed by dozens of financial institutions, including the bank. Which attack vector does this describe?
This is a supply chain compromise. The attacker exploited a trusted third-party vendor and used its legitimate update mechanism to reach many institutions at once, which differs from credential stuffing, denial-of-service traffic floods, or email impersonation fraud.
- ACredential stuffing against customer accounts
- BDistributed denial-of-service attack
- CSupply chain compromiseCorrect
- DBusiness email compromise
Explanation
Compromising a trusted vendor and distributing malicious code through its legitimate update channel is a supply chain attack. Credential stuffing reuses leaked passwords, DDoS overwhelms availability with traffic, and business email compromise relies on impersonation to induce payments. None involves a trusted software update.
Did you get it right without looking?
One question tells you little. A timed set on Case Study: Cyberthreats and Information Security Risks shows your real accuracy, how long you take and where you lose marks.
More Case Study: Cyberthreats and Information Security Risks questions
- A bank estimates that a ransomware outage of its trading platform would cost USD 2.0 million per hour in lost revenue for the first 3 hours,…
- A bank experienced a data breach in which attackers exfiltrated customer records over several months. The investigation shows that a known v…
- A risk manager reviews incident data showing that attackers increasingly compromise a bank's software vendor and use the vendor's trusted up…
- A bank scores three cyber controls on design effectiveness (D) and operating effectiveness (O), each as a percentage of risk reduction, and …
- A bank estimates a cyber outage of its online platform would occur once every 4 years on average. Each event would cost USD 2.4 million in l…
- A payments firm sets a recovery time objective (RTO) of 4 hours and a recovery point objective (RPO) of 15 minutes for its card authorizatio…