A bond portfolio has a market value of USD 50 million and a modified duration of 6.4. Using the duration approximation, what is the approximate change in portfolio value if yields rise by 25 basis points in a parallel shift?

The portfolio loses about USD 800,000. Modified duration times value times the yield change gives 6.4 x 50 million x 0.0025. Rising yields reduce bond prices, so the sign is negative.

  1. ADecrease of USD 800,000Correct
  2. BIncrease of USD 800,000
  3. CDecrease of USD 3,200,000
  4. DDecrease of USD 80,000

Explanation

Change = -ModDur x Value x dy = -6.4 x 50,000,000 x 0.0025 = -800,000. The increase option has the wrong sign. The USD 3.2 million option uses 25 bp as 0.01 instead of 0.0025... in effect 1% rather than 0.25%, which is a scaling error.

Did you get it right without looking?

One question tells you little. A timed set on Modeling Non-Parallel Term Structure Shifts and Hedging shows your real accuracy, how long you take and where you lose marks.

More Modeling Non-Parallel Term Structure Shifts and Hedging questions