A budget committee in Chennai sets a budget for a department that is prepared for a fixed level of activity and is not adjusted even if actual activity differs. What is such a budget called?
Such a budget is called a fixed budget. It is prepared for one predetermined activity level and is not revised when actual activity differs, unlike a flexible budget, which is recast for the actual level of activity.
- AFixed budgetCorrect
- BFlexible budget
- CZero base budget
- DMaster budget
Explanation
A fixed budget is designed for one level of activity and remains unchanged regardless of actual output. A flexible budget changes with activity levels. Zero base budgeting is a method of building budgets, and the master budget is the summary of all functional budgets.
Did you get it right without looking?
One question tells you little. A timed set on Budgets and Budgetary Control shows your real accuracy, how long you take and where you lose marks.
More Budgets and Budgetary Control questions
- Which budget is prepared first when the principal budget factor of a manufacturing company is a limitation on the quantity of raw material t…
- Gupta Engineering budgets for 10,000 units: sales Rs 20,00,000, variable cost Rs 12,00,000 and fixed cost Rs 5,00,000. Actual output and sal…
- Which statement best describes zero-based budgeting (ZBB)?
- Which statement about a flexible budget is correct?
- Sharma Components Ltd budgeted for 10,000 units: direct material ₹6 per unit, direct labour ₹4 per unit, variable overhead ₹2 per unit (all …
- Surya Plastics budgets sales of 8,000 units for the next quarter. Opening finished stock is 1,200 units and the desired closing stock is 1,7…