A CDO has a USD 500 million pool, funded by equity of USD 25 million (0%-5%), mezzanine of USD 75 million (5%-20%) and senior of USD 400 million (20%-100%). Pool losses are USD 60 million. The manager proposes that excess spread of USD 8 million is first used to cover losses before the waterfall applies, reducing net pool loss. What are the resulting losses to equity and mezzanine tranches, respectively?

Equity loses USD 25 million and mezzanine loses USD 27 million. Excess spread of USD 8 million reduces the pool loss from 60 to 52 million; equity absorbs the first 25 million, and the remaining 27 million is borne by the mezzanine tranche, which has 75 million capacity.

  1. AUSD 25 million and USD 27 millionCorrect
  2. BUSD 25 million and USD 35 million
  3. CUSD 25 million and USD 10 million
  4. DUSD 17 million and USD 0

Explanation

Net loss after excess spread = 60 - 8 = USD 52 million. Equity absorbs the first 25 million. The remaining 27 million falls on mezzanine, whose capacity is 75 million. Option with 35 ignores excess spread; 17 and 0 wrongly apply the spread to equity only.

Did you get it right without looking?

One question tells you little. A timed set on Credit Derivatives shows your real accuracy, how long you take and where you lose marks.

More Credit Derivatives questions