ACCA Applied Knowledge · Management Accounting · Cost classification
A company codes its costs so that the code 2-1 denotes production overhead and 2-2 denotes administration overhead. During the month, $6,400 of factory rent and $2,500 of head office audit fees were both posted to code 2-1. Total production overhead was reported as $21,000 after these postings, and no other errors exist. What is the correct production overhead after correcting the miscoding?
Correct production overhead is $18,500. The head office audit fees of $2,500 are an administration cost wrongly posted to the production code, so they are removed from the $21,000 total. The factory rent is a genuine production cost and stays in.
- A$21,000
- B$18,500Correct
- C$14,600
- D$23,500
Explanation
Factory rent correctly belongs in production overhead (2-1), so it stays. The audit fees of $2,500 are an administration cost and must be removed from production overhead: 21,000 - 2,500 = $18,500. Leaving it unchanged ignores the error. $14,600 wrongly removes the rent as well, and $23,500 adds the fees instead of removing them.
Did you get it right without looking?
One question tells you little. A timed set on Cost classification shows your real accuracy, how long you take and where you lose marks.
More Cost classification questions
- A company pays its sales staff a basic salary of $2,000 per month plus a commission of 3% of the value of sales made in the month. How would…
- Which of the following costs would be classified as a production (manufacturing) cost in a company that makes office chairs?
- Which of the following is an example of indirect labour in a manufacturing company?
- Which of the following is most likely to be a variable cost for a manufacturing company?
- A semi-variable cost was $14,000 when 2,000 units were produced and $19,000 when 3,000 units were produced. Using the high-low method, what …
- A furniture maker buys timber that becomes part of the tables it produces. Which classification of cost element best describes the timber?