A company finds that its monthly cost report reaches managers after two months, by which time wasteful spending has already continued. Which characteristic of an effective control system is most lacking?

Timeliness is lacking. An effective control system must report deviations quickly enough for corrective action before losses grow. A cost report arriving two months late lets wasteful spending continue unchecked, so the problem is delay in information, not the cost of control or inflexibility.

  1. AEconomy
  2. BFlexibility
  3. CSuitability
  4. DTimelinessCorrect

Explanation

An effective control system must give information in time so deviations can be corrected before they cause large losses. A two-month delay defeats this. Economy concerns cost of control versus benefit, and flexibility concerns adaptability to change; neither is the problem described.

Did you get it right without looking?

One question tells you little. A timed set on Principles of Management and Modern Approaches shows your real accuracy, how long you take and where you lose marks.

More Principles of Management and Modern Approaches questions