A company finds that its monthly cost report reaches managers after two months, by which time wasteful spending has already continued. Which characteristic of an effective control system is most lacking?
Timeliness is lacking. An effective control system must report deviations quickly enough for corrective action before losses grow. A cost report arriving two months late lets wasteful spending continue unchecked, so the problem is delay in information, not the cost of control or inflexibility.
- AEconomy
- BFlexibility
- CSuitability
- DTimelinessCorrect
Explanation
An effective control system must give information in time so deviations can be corrected before they cause large losses. A two-month delay defeats this. Economy concerns cost of control versus benefit, and flexibility concerns adaptability to change; neither is the problem described.
Did you get it right without looking?
One question tells you little. A timed set on Principles of Management and Modern Approaches shows your real accuracy, how long you take and where you lose marks.
More Principles of Management and Modern Approaches questions
- Under Taylor's differential piece-rate system, a worker who completes output at or above the standard is paid:
- At a Pune engineering unit, the owner appoints separate specialists for speed, repairs, inspection and discipline, and each specialist direc…
- Consider the statements about the controlling function. I: Controlling involves comparing actual performance with standards and taking corre…
- Which of the following is a feature of the quantitative (management science) approach?
- Consider the following statements about coordination: I. Coordination is the force that unifies the efforts of different departments towards…
- Match the feature of management in Column I with its meaning in Column II. Column I: (P) Pervasive (Q) Continuous (R) Intangible (S) Dynamic…