Skip to content

ACCA Applied Knowledge · Management Accounting · Standard costing system

A company makes one product. Each unit needs 4 kg of material that costs $5 per kg. Normal wastage is 20% of the input material. What is the standard material cost per unit of good output?

The standard material cost is $25 per unit. Because normal wastage is 20% of input, only 80% of input becomes good output, so each unit needs 4 divided by 0.8, or 5 kg of material. Multiplying 5 kg by $5 per kg gives $25.

  1. A$20.00
  2. B$24.00
  3. C$25.00Correct
  4. D$16.00

Explanation

Wastage is 20% of input, so good output is 80% of input. Input needed per good unit = 4 / 0.8 = 5 kg. Cost = 5 kg x $5 = $25. The $24 option wrongly adds 20% to the output requirement (4 x 1.2 = 4.8 kg).

Did you get it right without looking?

One question tells you little. A timed set on Standard costing system shows your real accuracy, how long you take and where you lose marks.

More Standard costing system questions