Skip to content

ACCA Applied Skills · Performance Management · Target costing

A company uses target costing for a new product. The target cost is $45 and the current estimated cost is $52. Value engineering identifies savings of $5 per unit. What is the remaining cost gap per unit?

The remaining cost gap is $2 per unit. The original gap is the $52 estimated cost less the $45 target, which is $7. Value engineering savings of $5 reduce this, leaving $2 still to be removed to reach the target cost.

  1. A$2Correct
  2. B$5
  3. C$7
  4. D$12

Explanation

Initial cost gap = 52 - 45 = $7. Savings of $5 reduce this to $2. Choosing $7 ignores the savings already identified, and $12 adds the savings instead of deducting.

Did you get it right without looking?

One question tells you little. A timed set on Target costing shows your real accuracy, how long you take and where you lose marks.

More Target costing questions