A company with a stable capital structure is appraising a project whose business risk is much higher than that of its existing operations. Which approach is most appropriate for the discount rate?

Use a discount rate reflecting the project's own systematic risk, for example derived from the betas of companies in a similar business. The existing WACC only reflects the average risk of current operations, so applying it to a much riskier project would understate the required return.

  1. AUse the company's existing WACC, since financing mix is unchanged
  2. BUse the current cost of debt, since the project will be debt financed
  3. CUse a rate reflecting the project's own systematic risk, such as one based on the beta of firms in similar businessCorrect
  4. DUse the dividend yield on the company's shares
  5. Use the risk-free rate, adding nothing for risk

Explanation

The existing WACC reflects the average risk of current operations. A project with different business risk should be discounted at a rate that reflects its own systematic risk, often estimated from the betas of comparable firms. Using the existing WACC would undervalue the risk and may accept poor projects.