ACCA Applied Skills · Financial Management · Adjusting for risk and uncertainty in investment appraisal
A company's normal cost of capital is 10%. A project has a higher business risk than the company's existing operations, so management adds a 4% risk premium and discounts at 14%. The project's cash flows are: outlay $100,000 now, then $60,000 at the end of years 1 and 2. Discount factors at 14%: year 1 0.877, year 2 0.769. What is the NPV at the risk-adjusted rate?
The NPV at 14% is negative $1,240. Present value of inflows is $60,000 multiplied by 1.646, giving $98,760, and deducting the $100,000 outlay leaves a deficit, so the project would be rejected on the risk-adjusted rate.
- A$8,760Correct
- B$98,760
- C$(1,240)
- D$18,760
Explanation
PV of inflows = 60,000 × (0.877 + 0.769) = 60,000 × 1.646 = $98,760. NPV = 98,760 − 100,000 = −$1,240. Wait: this is negative, so the correct figure is $(1,240). Using 14% the project is rejected.
Did you get it right without looking?
One question tells you little. A timed set on Adjusting for risk and uncertainty in investment appraisal shows your real accuracy, how long you take and where you lose marks.
More Adjusting for risk and uncertainty in investment appraisal questions
- Which statement about adjusting the discount rate for project risk is correct?
- Which of the following techniques is normally used to deal with uncertainty, rather than risk, in investment appraisal, because it does not …
- Which of the following is a recognised weakness of using the payback period as the only method of investment appraisal?
- Kestrel Ltd is appraising a project with three possible outcomes. Its analyst has estimated the probability of each outcome from past experi…
- An investment costs $150,000 now. Annual cash inflows for four years are $40,000 (probability 0.25), $60,000 (probability 0.45) or $80,000 (…
- A project has three possible outcomes: an NPV of $120,000 with probability 0.3, an NPV of $50,000 with probability 0.5, and an NPV of -$40,0…