ACCA Applied Skills · Financial Management · Adjusting for risk and uncertainty in investment appraisal

A project has three possible outcomes: an NPV of $120,000 with probability 0.3, an NPV of $50,000 with probability 0.5, and an NPV of -$40,000 with probability 0.2. What is the expected value of the project's NPV?

The expected NPV is $53,000. Each possible NPV is multiplied by its probability and the results are summed, including the negative outcome: 36,000 plus 25,000 minus 8,000. A simple average or the most likely outcome would ignore the probability weights.

  1. A$53,000Correct
  2. B$43,333
  3. C$61,000
  4. D$50,000

Explanation

EV = (0.3 × 120,000) + (0.5 × 50,000) + (0.2 × -40,000) = 36,000 + 25,000 - 8,000 = $53,000. $43,333 is a simple average that ignores the probabilities. $61,000 leaves out the negative outcome. $50,000 is only the most likely outcome.

Did you get it right without looking?

One question tells you little. A timed set on Adjusting for risk and uncertainty in investment appraisal shows your real accuracy, how long you take and where you lose marks.

More Adjusting for risk and uncertainty in investment appraisal questions