IAI Actuarial Core Principles · Economic Modelling · Valuing benefit guarantees using simulation
A control variate method estimates the cost of a guarantee using simulated payoff X. A control Y has known expected value 12.0 (from a closed-form formula). In 5,000 runs the sample mean of X is 8.40 and the sample mean of Y is 11.70. Using the control variate coefficient of 0.5, what is the adjusted estimate of E[X]?
The adjusted estimate is 8.55. The simulated control mean of 11.70 is below its true value of 12.0 by 0.30, so half of that shortfall, 0.15, is added to the raw estimate of 8.40.
- A8.25
- B8.55Correct
- C8.40
- D8.10
- 8.70
Explanation
Adjusted estimate = mean X + b(E[Y] - mean Y) = 8.40 + 0.5(12.0 - 11.70) = 8.40 + 0.15 = 8.55. Using the wrong sign gives 8.25, which is incorrect because the simulation under-estimated Y, so X is adjusted upward.
Did you get it right without looking?
One question tells you little. A timed set on Valuing benefit guarantees using simulation shows your real accuracy, how long you take and where you lose marks.
More Valuing benefit guarantees using simulation questions
- An insurer uses stochastic simulation to value a maturity guarantee on a unit-linked policy. It wants a market-consistent value consistent w…
- A unit-linked maturity guarantee promises the policyholder the greater of the unit fund value and a guaranteed sum at maturity. From the ins…
- For which purpose would an insurer most appropriately use real-world rather than risk-neutral scenarios?
- A life insurer values a guarantee at a future time horizon using nested (stochastic-on-stochastic) simulation: 1,000 outer real-world scenar…
- An actuary values a maturity guarantee on a unit-linked contract using 10,000 independent stochastic simulations of the fund value. She want…
- A life office hedges a maturity guarantee dynamically and rebalances only once a month. Which of the following is the main reason the hedge …