A control variate method estimates the cost of a guarantee using simulated payoff X. A control Y has known expected value 12.0 (from a closed-form formula). In 5,000 runs the sample mean of X is 8.40 and the sample mean of Y is 11.70. Using the control variate coefficient of 0.5, what is the adjusted estimate of E[X]?

The adjusted estimate is 8.55. The simulated control mean of 11.70 is below its true value of 12.0 by 0.30, so half of that shortfall, 0.15, is added to the raw estimate of 8.40.

  1. A8.25
  2. B8.55Correct
  3. C8.40
  4. D8.10
  5. 8.70

Explanation

Adjusted estimate = mean X + b(E[Y] - mean Y) = 8.40 + 0.5(12.0 - 11.70) = 8.40 + 0.15 = 8.55. Using the wrong sign gives 8.25, which is incorrect because the simulation under-estimated Y, so X is adjusted upward.

Did you get it right without looking?

One question tells you little. A timed set on Valuing benefit guarantees using simulation shows your real accuracy, how long you take and where you lose marks.

More Valuing benefit guarantees using simulation questions