A CSR audit report on Delta Power Ltd contains observations on delayed project milestones and weak documentation. What is the most appropriate next step in the audit process?
The report should be placed before the Board or CSR Committee, and implementation of the recommendations should be followed up. Reporting to governance and tracking corrective action completes the audit cycle and improves delay and documentation weaknesses in future CSR projects.
- ADestroy the working papers
- BPlace the report before the Board or CSR Committee and follow up on implementation of recommendationsCorrect
- CHide the findings from the Board to avoid conflict
- DClose the matter since the report is issued
Explanation
After reporting, findings go to those charged with governance, the Board or CSR Committee, and the auditor or company follows up to see that corrective action is taken. Concealing findings or ignoring follow-up defeats the audit's value.
Did you get it right without looking?
One question tells you little. A timed set on Social Impact Assessment and CSR Audit shows your real accuracy, how long you take and where you lose marks.
More Social Impact Assessment and CSR Audit questions
- Bharat Textiles Ltd wants to measure how its village skill-training project changed the incomes of trainees. It compares incomes of trained …
- Kaveri Pharma Ltd runs a health camp programme. Its CSR team builds a table linking inputs (doctors, medicines), activities (camps held), ou…
- Kaveri Industries Ltd plans a CSR school-building project in a tribal block. Before starting, its Board asks for an assessment that studies …
- Anand Steels Ltd spent its full CSR amount on a health camp. A later assessment shows many beneficiaries were from outside the area where th…
- Sagar Textiles Ltd, whose financial year ends on 31 March 2026, spent Rs 70 lakh of its Rs 1 crore CSR obligation. The Rs 30 lakh shortfall …
- During a CSR audit of Kaveri Steels Ltd, the auditor finds a project report from an implementation agency but no bills, bank statements or s…